TOPIC 05/1116 MINNOT STARTED

Demand guarantees and standby letters of credit

A promise that pays on a demand, not a shipment: what an independent undertaking is, who the four parties are, and what reaches a rail when one is called.

L1–L4 are part of the Pro pass

L0 Explain simply

Asha Traders has won a contract to supply fabric to a buyer abroad, and the buyer wants a promise. The invoice cannot give it one: an assurance that if Asha Traders takes the advance and never ships, the money comes back. (SYNTHETIC / TRAINING ONLY — every firm named here is invented.)

A bank can give that assurance. The instrument is a , and in the United States the same job is usually done by a .

Here is the part that surprises people. The promise is not a copy of the contract. It is a separate promise, and the bank that gives it does not judge the trade at all.

Set it beside the you have already met. There, a bank pays because goods were shipped and the right documents arrived. Here, a bank pays because the beneficiary said the other side failed, in the form the promise asked for.

In this performance-backstop example, a successful deal normally leaves the undertaking unused. That expectation is not a definition of every standby: the preface also describes a direct-pay standby, supporting payment when due without requiring a default.

That is the whole idea, and the rest of this topic works out what follows from it. Who the parties are, and why there are sometimes four of them. What a bank checks before it pays. What actually moves on a when a guarantee is called. And why this instrument attracts a particular kind of fraud.

PICTURE IT

A neighbour's written promise to a landlord

A tenant wants to rent a flat, and the landlord wants some assurance. A neighbour who is trusted by both writes a short promise card. If the landlord sends a signed request before a set date, with a note saying what the tenant failed to do, the neighbour will pay. The neighbour does not visit the flat. The neighbour does not ask who is right. The neighbour only checks that the request matches the card. If the tenant behaves well, the card stays in a drawer and runs out. If the landlord will not trust a stranger's card, the landlord's own local neighbour writes the card instead. The first neighbour then promises to back that local neighbour.

THE REAL JOB If the seller fails, a bank pays when the buyer asks in the form the promise sets, so the buyer can trade without trust.

  1. The applicant asks a bank to give a promise
  2. The guaranteeing bank issues the undertaking to the beneficiary
  3. The beneficiary sends a demand
  4. The guaranteeing bank checks the demand against the wording
  5. If compliant, the guaranteeing bank pays by an ordinary transfer
From the promise to the money, in order

HOW THE PICTURE MAPS

How each part of the picture matches the payment
In the pictureIn the payment
The tenant who needs the flatThe applicant, whose duty to the beneficiary is backed
The landlord holding the cardThe beneficiary, who may ask for payment
The neighbour who writes the cardThe guaranteeing bank, the bank that issues the undertaking
The promise card itselfThe demand guarantee, a separate promise from the contract
The signed request with a note and a dateThe demand, which is compliant only if it meets every condition set
The landlord's own local neighbour who will not trust a stranger's cardThe local bank that issues instead, backed by a counter-guarantee
The card left in the drawer until it runs outAn unused guarantee that expires when the deal goes well

WHERE THIS PICTURE STOPS

  • A real neighbour could still have an opinion about who is right. A bank under this instrument gives no opinion on whether the trade failed, and it is not asked to. Its duty does not depend on the underlying deal.
  • The picture has one card. The four-party case has two undertakings, and the picture has no counterpart for the counter-guarantee beyond the local neighbour.
  • A card is only words. Money moves when the guarantee is honoured, and it then reaches a payment rail as an ordinary transfer, which the picture does not show.
  • The picture shows no rule set. A real undertaking sets its own conditions, and the rule set the parties choose changes what a bank may do with an incomplete demand.
  • The picture models a performance backstop. Direct-pay standbys need not require default; mandatory law, fraud exceptions and court intervention remain relevant.

HOOK

The bank reads the demand, not the deal.

REMEMBER IT THIS WAY

A sequence: the real steps, in order.

With a local bank, a call travels back in four steps: ask, pass on, pay, debit.

What each part of the trick stands for
In the trickWhat it stands for
askthe beneficiary asks the local bank for payment
pass onthe local bank asks under the counter-guarantee
paythe applicant's bank pays the local bank under the counter-guarantee, which backs the local bank's own undertaking to the beneficiary
debitThe applicant reimburses its bank under its own agreement, collateral or credit arrangements; not necessarily an automatic immediate account debit.

It is a simple local-issuer example; each demand, expiry and payment condition is independent; a counter-demand may not require prior actual local payment.

TELL A FRIEND

An independent undertaking to pay against a demand meeting its terms, subject to applicable law and exceptions.

OFTEN MIXED UP WITH Trade finance payments. A commercial commonly pays on a complying shipment presentation. This guarantee example is a performance backstop; neither product name settles every possible demand condition.

Sources & standards — 2 sources
  1. Official requirement

    United Nations Convention on Independent Guarantees and Stand-by Letters of Credit (New York, 1995) ↗ — United Nations Commission on International Trade Law · Opened UN1995 Convention arts 1–3,6,19–20; scope must be established before applying its payment/fraud provisions.

    1995 Convention: articles1–3scope/independence,6counterguarantee and19–20fraud/abuse/courtintervention. · Effective 2000-01-01 · Checked 2026-11-06

    Opened resolution annex6November 2026. Applicability must be checked for an instrument; no assertion every country or undertaking is governed by this Convention.

  2. Scheme-specific rulePublication No. 590, approved January 1999

    International Standby Practices (ISP98), Publication 590 ↗ — International Chamber of Commerce (ICC) · Opened ISP98 preface: standby functions including direct pay, adoption for independent undertakings and mandatory-law boundary.

    ISP98 identity and the opened preface: descriptive standby functions include direct pay without default; independent undertakings can adopt ISP; mandatory law controls. · Checked 2026-11-06

    ICC primary preface opened6November 2026. This is not a claim to have re-read every rule. The prior exclusive “no other instrument” interpretation was contradicted by the preface.

CURRENT AS CHECKED

2 FIGURES
  • Rule sets of the International Chamber of Commerce (ICC) named on this site: URDG (Uniform Rules for Demand Guarantees) 758, ISP98 (International Standby Practices), ISBP (International Standard Banking Practice) 821 and Incoterms 2020 — edition and date

    The (ICC) publishes the rule sets that trade instruments adopt by naming them. The , URDG 758, came into force on 1 July 2010 as ICC Publication 758E. The International Standby Practices, ISP98, are ICC Publication 590, approved in January 1999. ISBP 821, the International Standard Banking Practice for examining documents under the Uniform Customs and Practice (UCP 600), was published in July 2023. Incoterms 2020 hold eleven trade terms and came into force on 1 January 2020.

    An instrument is read under the edition it names. No successor to any of these four was found in the ICC pages seen. So the review date is a periodic check and is not tied to an announced event.

    CHECKED 2026-10-04RECHECK BY 2027-04-04

    Sources & standards — 4 sources
    1. Scheme-specific rulePublication No. 758E, 2010 edition

      Uniform Rules for Demand Guarantees (URDG 758) ↗ — International Chamber of Commerce (ICC) · Publication 758E and its 1 July 2010 start — search excerpt of the page of the International Chamber of Commerce (ICC), page not opened

      The Uniform Rules for Demand Guarantees, International Chamber of Commerce Publication 758E. They are written for demand guarantees and for the counter-guarantees behind them. They apply to a guarantee because the guarantee says so.

      Cited for the rules' identity and scope only. The International Chamber of Commerce describes them as covering each stage of a guarantee's life: drafting, presenting a demand, examining it, paying and ending. No article is quoted or paraphrased. · Effective 2010-07-01 · Checked 2026-10-04

      Seen as search excerpts of the International Chamber of Commerce's own pages on the access date. The page was not opened, because iccwbo.org could not be fetched.

      The excerpts agree on four points. The rules came into force on 1 July 2010. The text has 35 articles. A United Nations body endorsed it at a 2011 session in Vienna. It is a Chamber publication, and the Chamber sells it.

      The rules text is sold, so it was not read. This entry supports what the rulebook is and what it is for, and nothing inside it. The sourcing negative icc-trade-finance-rule-texts explains why.

    2. Scheme-specific rulePublication No. 590, approved January 1999

      International Standby Practices (ISP98), Publication 590 ↗ — International Chamber of Commerce (ICC) · Publication 590 and its January 1999 approval — search excerpt of the International Chamber of Commerce (ICC) Academy page, page not opened

      ISP98 identity and the opened preface: descriptive standby functions include direct pay without default; independent undertakings can adopt ISP; mandatory law controls. · Checked 2026-11-06

      ICC primary preface opened6November 2026. This is not a claim to have re-read every rule. The prior exclusive “no other instrument” interpretation was contradicted by the preface.

    3. Scheme-specific rulePublication No. 821E, July 2023

      International Standard Banking Practice (ISBP 821) for the Examination of Documents under the Uniform Customs and Practice ↗ — International Chamber of Commerce (ICC) · Publication 821E, published July 2023 — search excerpt of the International Chamber of Commerce (ICC) Academy page, page not opened

      The International Standard Banking Practice for the examination of documents under the Uniform Customs and Practice for Documentary Credits (UCP 600). It is International Chamber of Commerce Publication 821E, published in July 2023. It shows how the principles of UCP 600 apply to everyday documents. These include an invoice, a transport document, an insurance document and a certificate of origin.

      Cited for its identity, its scope and one statement: it does not amend UCP 600. It explains how the UCP's practices are applied. No paragraph of it is quoted. · Checked 2026-10-04

      Seen as search excerpts of the International Chamber of Commerce's own pages on the access date. The page was not opened, because iccwbo.org could not be fetched.

      The excerpts agree that this edition covers practices taken from opinions that the Chamber's national committees approved since 2013. They also agree that it does not amend the Uniform Customs and Practice.

      The text is sold, so it was not read. Identity and scope only.

    4. Scheme-specific ruleIncoterms 2020

      Incoterms 2020 rules ↗ — International Chamber of Commerce (ICC) · Eleven rules, in force 1 January 2020 — search excerpt of the page of the International Chamber of Commerce (ICC), page not opened

      Incoterms 2020: eleven three-letter trade terms that a contract for the sale of goods can name. The International Chamber of Commerce (ICC) says they define important responsibilities of buyers and sellers for delivering goods. It also says they set how costs and risks are shared.

      Cited for the rules' identity, scope and edition. The ICC sells the full text, so no rule is quoted. · Effective 2020-01-01 · Checked 2026-10-04

      Seen as search excerpts of the International Chamber of Commerce's own pages on the access date. The page was not opened, because iccwbo.org could not be fetched.

      The excerpts agree that the rules came into force on 1 January 2020 and that there are eleven terms. An earlier check of this page is recorded in the sourcing negative icc-trade-finance-rule-texts. It found that the complete text is sold and that a checklist and flow charts are free.

      What the rules leave out comes from other sources. See munichre-incoterms-2020.

  • Demand guarantee rules, Article 20(a)

    Under Article 20(a) of the (URDG 758), a guarantor has five business days after the day of presentation to examine a demand and decide whether it complies. The guarantee can set a different period. A demand that says it will be completed later does not start the clock until it is complete.

    CHECKED 2026-10-12RECHECK BY 2027-04-30

    Sources & standards — 3 sources
    1. Scheme-specific rule

      International Chamber of Commerce expert decision 344 on examining a demand under the Uniform Rules for Demand Guarantees ↗ — International Chamber of Commerce · Decision 344, quoting Article 20(a): the guarantor examines the demand within five business days of presentation (search excerpt, page not opened)

      An expert decision of the Chamber that quotes Article 20(a) of the demand guarantee rules.

      Cited for the rule that the bank that issued a guarantee must examine a demand within a fixed number of business days after presentation. The days themselves are in the dated fact urdg-758-article-20a-examination-period. · Checked 2026-10-12

      Known from web-search excerpts on the access date, page not opened. The publisher's own domain cannot be fetched from the authoring environment, so nothing is quoted from the page itself.

      Other decision pages in the Chamber's library were seen only as results and are not cited.

    2. Market practice

      International Chamber of Commerce guidance paper on the impact of the pandemic on trade finance ↗ — International Chamber of Commerce · Days counted by the hours a bank works; period lengthened by amendment all parties accept (search excerpt, page not opened)

      A Chamber guidance paper from the first months of the pandemic.

      Cited for two points about the examination period in the demand guarantee rules. The days are counted by the hours the bank actually works, and parties can lengthen the period by an amendment all of them accept. · Checked 2026-10-12

      Known from web-search excerpts on the access date, page not opened. The publisher's own domain cannot be fetched from the authoring environment, so nothing is quoted from the page itself.

      A 2020 paper. It is guidance, not rule text.

    3. Scheme-specific rulePublication No. 758E, 2010 edition

      Uniform Rules for Demand Guarantees (URDG 758) ↗ — International Chamber of Commerce (ICC) · Identity and scope of URDG 758 only (search excerpt, page not opened)

      The Uniform Rules for Demand Guarantees, International Chamber of Commerce Publication 758E. They are written for demand guarantees and for the counter-guarantees behind them. They apply to a guarantee because the guarantee says so.

      Cited for the rules' identity and scope only. The International Chamber of Commerce describes them as covering each stage of a guarantee's life: drafting, presenting a demand, examining it, paying and ending. No article is quoted or paraphrased. · Effective 2010-07-01 · Checked 2026-10-04

      Seen as search excerpts of the International Chamber of Commerce's own pages on the access date. The page was not opened, because iccwbo.org could not be fetched.

      The excerpts agree on four points. The rules came into force on 1 July 2010. The text has 35 articles. A United Nations body endorsed it at a 2011 session in Vienna. It is a Chamber publication, and the Chamber sells it.

      The rules text is sold, so it was not read. This entry supports what the rulebook is and what it is for, and nothing inside it. The sourcing negative icc-trade-finance-rule-texts explains why.

MESSAGES INVOLVED

PRACTISE AND KEEP

IMPLEMENTATION RESOURCES

1 RESOURCE

EVIDENCE AT ARM'S REACH

Apply the base message definition first, then the scheme or infrastructure profile that governs this topic.

An XSD checks XML structure. A usage guideline adds profile rules, conditional fields, code restrictions, and business controls. XSD-valid does not mean scheme-compliant.

Field matrixSwift MT

MT760 field matrix

PRO PASS
Sources for this topic — 12 sources
  1. Official requirement

    United Nations Convention on Independent Guarantees and Stand-by Letters of Credit (New York, 1995) ↗ — United Nations Commission on International Trade Law · Articles 2, 3 and 6 — what an undertaking is, what independence means, and what a counter-guarantee is

    1995 Convention: articles1–3scope/independence,6counterguarantee and19–20fraud/abuse/courtintervention. · Effective 2000-01-01 · Checked 2026-11-06

    Opened resolution annex6November 2026. Applicability must be checked for an instrument; no assertion every country or undertaking is governed by this Convention.

  2. Market practice2019 amendment to the 2017 paper

    Trade Finance Principles ↗ — The Wolfsberg Group, International Chamber of Commerce and BAFT · The appendix covering guarantees and standby letters of credit

    The industry statement of the financial-crime controls banks apply to trade finance: the role a financial institution plays in addressing money laundering, terrorist financing, bribery and proliferation financing, and in complying with sanctions and embargoes. Its appendices take the product families one at a time — documentary credits, bills for collection, guarantees and standby letters of credit. And open account — and Appendix III describes, through a simplified scenario, the control activities each bank in a guarantee or standby chain performs. · Checked 2026-11-06

    Actual ICC-hosted 2019 PDF read on 6 November 2026: cover/rights/foreword, complete core pp 8–23 and Appendix I pp 33–46. Other appendices not certified in this pass. Industry guidance, not legislation. Technology observations and cited laws are dated. Source p2 requires permission for commercial/adapted use and permits website availability only through a publisher web-page link, not a direct document link. Original figures remain held. A source footnote expands RMA incorrectly; the lesson uses current Relationship Management Authorisation terminology.

  3. Scheme-specific rule

    ICC rules for documentary credits (UCP 600) and related trade-finance rules ↗ — International Chamber of Commerce (ICC) · UCP 600,2007 revision; ICC Digital Library text opened for the specific role, independence, examination and refusal claims.

    UCP 600,2007 revision: incorporated contractual rules for documentary credits, including standbys to the extent applicable. Specific claims use the inspected articles, including independence, issuer/adviser/nominee/confirmer roles, examination and refusal. · Checked 2026-11-06

    ICC Digital Library text opened6 November 2026. This replaces an earlier identity-only/search-excerpt access note. Rules are not legislation; read incorporation, modifications and applicable mandatory law. V46 independently read complete Articles 1–20 on6 November; no full39-article certification. Paraphrases use incorporation, role, amendment, examination and refusal scope; mandatory applicable law remains separate.

  4. Scheme-specific rule

    Swift Standards MT (annual standards releases) ↗ — Swift · Category 7 documentary credits and guarantees

    Defines the MT message standards (including MT101, MT103, MT202/202 COV, and the MT9xx statement messages) exchanged over the Swift FIN network, maintained through annual standards releases. · Checked 2026-11-12

    Full field-level specifications live in the Swift Knowledge Centre User Handbook behind a swift.com login. Coexistence for in-scope FI-to-FI payment instructions ended on 22 November 2025, but treatment differs by MT: some instructions are NAKed and selected messages can enter temporary, chargeable contingency conversion. Reporting, initiation, investigations and correspondence follow separate roadmaps.

    Re-checked on 2026-10-04 by web search for the schedule of Standards Release 2026. Only search excerpts of the Standards Releases page were seen; the page was not opened. They said the deferred part of the release, which holds MT messages outside category 1, ISO 20022 securities and funds messages, tracker messages and exceptions and investigations messages, now has a date of 12 June 2027. They said the first target was the first quarter of 2027, and that the later date follows industry feedback about other change work, including the European move to T+1 settlement. An audit note in docs/research dated 29 September 2026 recorded the same date from the same page.

    Re-checked 12 November 2026 via Swift Standards Releases schedule: SR2025 remains the in-force annual MT release pending the deferred SR2026 package.

  5. Regulatory guidance

    Public service announcement — fraud actors scamming investors through made-up standby letters of credit ↗ — Federal Bureau of Investigation, Internet Crime Complaint Center · Fabricated standby letters of credit and fabricated Swift confirmations in advance-fee schemes

    Law-enforcement description of the advance-fee pattern in which fabricated bank instruments and fabricated SWIFT confirmations — commonly cited as MT760 or MT799 — are used to extract fees before any instrument exists. · Checked 2026-08-03

    Search excerpts only, page not opened.

  6. Simplified educational illustration

    Payments Signal editorial teaching models — Payments Signal

    This site's own simplified teaching models. · Checked 2026-07-12

    What this simplifies: Asha Traders and its buyer are invented, and the guarantee's wording is written to make the examination easy to read. No article of any rule set is quoted, because the texts are sold rather than published.

    Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.

  7. Scheme-specific rulePublication No. 758E, 2010 edition

    Uniform Rules for Demand Guarantees (URDG 758) ↗ — International Chamber of Commerce (ICC) · Identity and scope of URDG 758 — search excerpt of the ICC's page, page not opened; the text is sold and no article is quoted

    The Uniform Rules for Demand Guarantees, International Chamber of Commerce Publication 758E. They are written for demand guarantees and for the counter-guarantees behind them. They apply to a guarantee because the guarantee says so.

    Cited for the rules' identity and scope only. The International Chamber of Commerce describes them as covering each stage of a guarantee's life: drafting, presenting a demand, examining it, paying and ending. No article is quoted or paraphrased. · Effective 2010-07-01 · Checked 2026-10-04

    Seen as search excerpts of the International Chamber of Commerce's own pages on the access date. The page was not opened, because iccwbo.org could not be fetched.

    The excerpts agree on four points. The rules came into force on 1 July 2010. The text has 35 articles. A United Nations body endorsed it at a 2011 session in Vienna. It is a Chamber publication, and the Chamber sells it.

    The rules text is sold, so it was not read. This entry supports what the rulebook is and what it is for, and nothing inside it. The sourcing negative icc-trade-finance-rule-texts explains why.

  8. Scheme-specific rulePublication No. 590, approved January 1999

    International Standby Practices (ISP98), Publication 590 ↗ — International Chamber of Commerce (ICC) · Identity, scope and purpose of ISP98 — search excerpt of the ICC Academy page, page not opened; no article is quoted

    ISP98 identity and the opened preface: descriptive standby functions include direct pay without default; independent undertakings can adopt ISP; mandatory law controls. · Checked 2026-11-06

    ICC primary preface opened6November 2026. This is not a claim to have re-read every rule. The prior exclusive “no other instrument” interpretation was contradicted by the preface.

  9. Scheme-specific rule

    Swift, MT (message type) Category 7 enhancements overview ↗ — Swift · Three sequences, and up to seven extension messages after one MT760; search excerpt only, page not opened

    Swift's overview of the guarantee and standby redesign. Search excerpts show the three sequences of the new guarantee message MT760. They also show that up to seven extension messages (MT761) can follow one MT760. · Checked 2026-10-12

    An overview deck, so it states the design and not every field. Known only from a web-search excerpt; the page was not opened.

  10. Scheme-specific rule

    International Chamber of Commerce expert decision 344 on examining a demand under the Uniform Rules for Demand Guarantees ↗ — International Chamber of Commerce · Decision 344 quoting Article 20(a); search excerpt, page not opened

    An expert decision of the Chamber that quotes Article 20(a) of the demand guarantee rules.

    Cited for the rule that the bank that issued a guarantee must examine a demand within a fixed number of business days after presentation. The days themselves are in the dated fact urdg-758-article-20a-examination-period. · Checked 2026-10-12

    Known from web-search excerpts on the access date, page not opened. The publisher's own domain cannot be fetched from the authoring environment, so nothing is quoted from the page itself.

    Other decision pages in the Chamber's library were seen only as results and are not cited.

  11. Scheme-specific rule

    International Chamber of Commerce expert decision 388 on a rejection notice under the Uniform Rules for Demand Guarantees ↗ — International Chamber of Commerce · Decision 388 on URDG 758 Article 24(d), (e) and (f): one rejection notice that states each discrepancy; the notice goes without delay and by the article's deadline; a guarantor that fails (d) or (e) cannot claim the demand does not comply; search excerpt, page not opened

    An expert decision of the Chamber that applies Article 24(d), (e) and (f) of the demand guarantee rules.

    Cited for three points about rejecting a demand. The guarantor gives one notice that rejects the demand and states each discrepancy. The notice goes without delay and by a deadline that the article sets. A guarantor that does not follow those two steps cannot later claim the demand did not comply. · Checked 2026-10-17

    Known from a web-search excerpt on the access date, page not opened. The excerpt gives the decision's account of Article 24(d), (e) and (f), and says the panel applied (f) to a rejection sent after the deadline. Nothing is quoted from the page itself.

    A second search, of a law firm's commentary (Bryan Cave Leighton Paisner, URDG 758: finally tested and it does what it says on the tin), agreed on (d) and (e) at excerpt level. That page was not opened and is not cited.

    The rules text is sold, so it was not read. The sourcing negative icc-trade-finance-rule-texts explains why.

  12. Market practice

    International Chamber of Commerce guidance paper on the impact of the pandemic on trade finance ↗ — International Chamber of Commerce · Business days counted by the hours a bank works; search excerpt, page not opened

    A Chamber guidance paper from the first months of the pandemic.

    Cited for two points about the examination period in the demand guarantee rules. The days are counted by the hours the bank actually works, and parties can lengthen the period by an amendment all of them accept. · Checked 2026-10-12

    Known from web-search excerpts on the access date, page not opened. The publisher's own domain cannot be fetched from the authoring environment, so nothing is quoted from the page itself.

    A 2020 paper. It is guidance, not rule text.

Deepest material on this page: L4 — Standards & sources. Where a topic stops short of implementation depth, that is a deliberate coverage decision, not an oversight — see coverage.