Entry and exit criteria

Agree in advance what must be true before testing starts, when to pause, and what must be true before it is called finished. It ends arguments.

L1–L4 are part of the Pro pass

L0 Explain simply

Analogy: a train leaves and arrives on conditions. A train leaves only when the doors are shut and the signal is green. It counts as arrived only when it is at the platform and the doors open. If a signal fails on the way, it stops until the signal is fixed.

Daily List is a to-do list app. Mei, the test lead, wants the team to agree on conditions like these for the sharing release. Without them, the team argues at the end about whether testing is done.

Mei writes three short lists. What must be true before testing starts. What makes the team pause. What must be true before the team calls testing finished. Nina, the product owner, reads the lists and says yes.

The lists have names. are the start list. are the pause list. Exit criteria are the finished list.

The picture has a limit. A train has one signal that anyone can see. Testing has many conditions, and people may disagree on them. That is why they are written down.

(SYNTHETIC / TRAINING ONLY: Daily List and every person named in this lesson are invented.)

PICTURE IT

The picture is the one the lesson above opens with. The table below shows how each part of it matches the software.

THE REAL JOB Agreeing in advance when to start, when to pause and when to stop testing.

  1. Doors shut
  2. Signal fails
  3. Pause and fix
  4. Arrive and report
Start, pause, stop

HOW THE PICTURE MAPS

How each part of the picture matches the software
In the pictureIn the software
Doors shut and signal greenEntry criteria
A failed signal on the trackSuspension criteria
At the platform with doors openExit criteria
The conductor's checklistThe written lines two people can agree on

WHERE THIS PICTURE STOPS

  • A train has one signal anyone can see. Testing has many conditions people may dispute.
  • A train cannot choose to leave with the doors open. A team can release without meeting a criterion if someone accepts the risk.
  • The picture has no Definition of Done. That is a story-level checklist.

HOOK

Start, pause, stop.

REMEMBER IT THIS WAY

A contrast: two neighbours told apart by one test.

Three yes-or-no questions: can we start, must we pause, are we finished. answer the first, the second, exit criteria the third.

What each part of the trick stands for
In the trickWhat it stands for
Can we startEntry criteria are the start list
Must we pauseSuspension criteria are the pause list
Are we finishedExit criteria are the finished list

People may still disagree on a line, so write each one down.

TELL A FRIEND

A train that leaves on conditions and arrives on conditions. Entry is about start, suspension is about pause, exit is about finish.

OFTEN MIXED UP WITH Writing a test plan. The plan lesson says where the criteria sit in a plan. This lesson says how to write them.

PRACTISE AND KEEP

Sources for this topic — 9 sources
  1. Market practice

    ISTQB Certified Tester Foundation Level Syllabus v4.0.1 ↗ — International Software Testing Qualifications Board · Section 5.1.3, entry criteria and exit criteria, and their link to the Definition of Done in agile work (confirmed against the syllabus, read in full text from a mirror copy of the publisher PDF, v4.0.1, 15 September 2024)

    The examinable statement of what a foundation-level tester is expected to know: six chapters, 64 learning objectives, each tagged K1 Remember, K2 Understand or K3 Apply, plus the test-design techniques the qualification names and groups as black-box, white-box and experience-based.

    Used here for the test-craft questions a Payment Quality Assurance Analyst and a Production Support Analyst are asked. It is cited for what the syllabus says a tester must be able to do, never as a rule about how payments work. · Checked 2026-11-07

    v4.0.1 is dated 15 September 2024 and is a list of corrections to v4.0 (21 April 2023) that reworded six learning objectives — not a cosmetic reissue. 78 pages.

    Two traps this entry exists to stop. v4.0.2 is the German edition (1 March 2025, 94 pages), so sorting by version number reaches the wrong document. And the widely-repeated per-chapter question allocation "8 / 5 / 4 / 11 / 9 / 3" is wrong: it is 8 / 6 / 4 / 11 / 9 / 2, derived from three official sample-exam answer keys and confirmed against the Exam Structure Tables.

    The single most consequential detail for a question bank: white-box coverage — statement and branch — is K2 "Explain", not K3 "Apply" (FL-4.3.1, FL-4.3.2, FL-4.3.3), and MC/DC, path and condition coverage are declared out of scope in §4.3. A question asking a candidate to compute branch coverage is testing something this syllabus does not.

    Read through a mirror, because the publisher's own domain could not be fetched (a reachability gap, not a statement about the publisher). A 403 there is a policy refusal and says nothing about whether the document exists or is reachable elsewhere.

    Anyone on an unrestricted network should open the canonical URL above and confirm the section and page numbers cited against it. Every claim drawn from this entry is written so that it can be checked against a numbered page.

    Read from two independent PDF-to-markdown conversions mirrored on raw.githubusercontent.com. They are treated as faithful because they were produced by unrelated parties with different tooling, agree on the full 64-item objective set including wording, and reproduce the same internal inconsistency present in the source PDF. Chapter 1 reads "testware that supports" where Appendix B reads "that support". A conversion artefact does not replicate across two toolchains.

    The licence permits attributed non-commercial extracts and use as the basis for articles. Whether a site that sells a pass may rely on that is an owner's decision, not this entry's.

    7 November 2026 review: actual publisher PDF 4.0.1, 15 September 2024, 78 pages, front matter/copyright and relevant numbered operative sections 0.5–0.10 and chapters 1–6 compared with CTFLpractice lessons. Earlier mirror/search descriptions are historical access records. TheK2 white-box objectives require explanation; the source does not justify a categorical ban on small numeric illustrations that support explanation. Later Exam Rules 1.2§4.1.4 usesK2 for keyword definitions, while syllabus§0.5 usesK1; keep dated scopes distinct. No copied questions or figure assets.

  2. Market practice

    The Scrum Guide — The Definitive Guide to Scrum: The Rules of the Game (November 2020) ↗ — Ken Schwaber and Jeff Sutherland · The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product (search excerpt, page not opened)

    The framework definition itself: three accountabilities, five events, three artifacts with their commitments, and the five Scrum values. Thirteen pages, about 3,956 words, CC BY-SA 4.0.

    Used here for the agile-delivery questions a Payments Business Analyst, a Payment Quality Assurance Analyst and a Payments Product Manager are asked — and, as often, for what the Guide does not say. Additional actual read scope7November2026: Official Scrum Guide November2020, actual ProductBacklog/refinement, SprintPlanning and SprintReview sections read7November2026: emergent ordered work, ongoing refinement, Done-within-Sprint readiness, possible planning refinement, Developer sizing/selection and feedback. No mandatory1–2Sprint buffer, user-story format or universal all-questions-answered rule; no whole-guide read claimed in this pass. · Checked 2026-08-18

    Still current in August 2026. There is no 2025 or 2026 revision of the Guide.

    The confusable document is a rename. "Scrum Guide Expansion Pack" (v2025.6) became "Scrum Guide Expanded" (v2026.1, 18 January 2026), published at scrumexpansion.org by Jocham, Coleman and Sutherland. Same URL path, different name, and Jeff Sutherland co-authors both it and the Guide — which is exactly the hook that makes wrong credit plausible. It is not a version of the Scrum Guide.

    Nine terms interview answers routinely attribute to Scrum appear zero times in the Guide: story points, velocity, Definition of Ready, sprint zero, user stories, acceptance criteria, grooming, T-shirt sizing, planning poker. So do "estimate" and "estimation".

    Two that are usually said to be absent and are present, which is why this paragraph exists: burn-down charts are named once and subordinated — "Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism" — and backlog refinement is defined as "an ongoing activity". What is absent is refinement as an event, and the absent word is "grooming".

    The Guide does require Product Backlog items to acquire a size, and puts sizing on the Developers, while naming no unit, scale or technique. It says "accountabilities", not "roles"; five events, not four; never "ceremony".

    Read through a mirror, because the publisher's own domain could not be fetched (a reachability gap, not a statement about the publisher). A 403 there is a policy refusal and says nothing about whether the document exists or is reachable elsewhere.

    Anyone on an unrestricted network should open the canonical URL above and confirm the section and page numbers cited against it. Every claim drawn from this entry is written so that it can be checked against a numbered page.

    Read in full from three independent mirrors that agree byte-for-byte on section structure, on the CC BY-SA 4.0 footer, on word count to within four words, and on all sixteen term-frequency counts above. Edition confirmed as 2020 specifically by zero occurrences of "Development Team" and thirteen of "Product Goal". Actual selected sections above read; prior metadata and wider source-use notes preserved. No full member book or adjacent legacy scheduling rule is implied.

  3. Market practice

    Definition of Done vs. Definition of Ready (Scrum Alliance) ↗ — Scrum Alliance · A Definition of Done is a shared checklist for finished work; a Definition of Ready is a checklist for work that may start (search excerpt, page not opened)

    Article saying the Definition of Done is a shared understanding of what complete means and is a core part of Scrum, while the Definition of Ready is an optional tool that can cause delay if it grows heavy. Practitioner guidance. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  4. Market practice

    Sample test plan (ReqTest) ↗ — ReqTest · Suspension criteria cover situations that stop testing or make it pointless; resumption criteria apply once the cause is fixed (search excerpt, page not opened)

    Describes common test plan sections, including approach and suspension and resumption criteria. Practitioner guidance, not a standard. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Version: Web page, no edition number. Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  5. Market practice

    Stopping heuristics (DevelopSense testing posts) ↗ — DevelopSense · Time's Up, Piñata and Mission Accomplished from DevelopSense pages (search excerpts, pages not opened; secondary summaries of Bolton's article, original not found). Diminishing returns from TestRail/bug0 practitioner posts. MoT thread 49346 is the learner question. Heuristics presented as fallible, as the sources do.

    Names stopping heuristics such as Time's Up and Piñata and says they are context-dependent. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  6. Market practice

    7 Ways to Define 'Enough' Testing ↗ — TestRail (Gurock blog) · Time's Up, Piñata and Mission Accomplished from DevelopSense pages (search excerpts, pages not opened; secondary summaries of Bolton's article, original not found). Diminishing returns from TestRail/bug0 practitioner posts. MoT thread 49346 is the learner question. Heuristics presented as fallible, as the sources do.

    Practitioner list of signs testing is enough, including diminishing returns. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  7. Market practice

    Rules: enough testing ↗ — SSW · Time's Up, Piñata and Mission Accomplished from DevelopSense pages (search excerpts, pages not opened; secondary summaries of Bolton's article, original not found). Diminishing returns from TestRail/bug0 practitioner posts. MoT thread 49346 is the learner question. Heuristics presented as fallible, as the sources do.

    Lists stopping heuristics (Time's Up, Piñata, Mission Accomplished, others). · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  8. Market practice

    Suspension and resumption criteria ↗ — TMAP (TMAP.net) · TMAP page on suspension and resumption: once the condition is lifted the affected part is tested again from the start; search excerpt, page not opened.

    Suspension examples are missing infrastructure or a test-blocking defect; once lifted, the affected part is tested again from the start. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  9. Market practice

    ISTQB Certified Tester Advanced Level Test Management Syllabus v3.0 (PDF) ↗ — International Software Testing Qualifications Board (ISTQB) · Section 1.4.3 (printed page 36): test plan types (master, level, quality characteristic, iteration); test objectives and exit criteria defined with the S.M.A.R.T. method: specific, measurable, achievable, relevant, timely; examples of test objectives; environments may not be available at the same time; version 3.0 of 2024-05-03, mirror copy of the publisher PDF, version checked against front matter, opened

    Version 3.0 syllabus (3 May 2024), read in full text. Used for the objective ids and levels, risk-based testing, the project test strategy, reporting, defect management, the four areas of competence and the cost of quality. It has no section on outsourced or distributed testing. Paraphrased, not quoted. · Checked 2026-11-07

    Text read in full from a mirror copy of the publisher PDF (ISTQB syllabus CTAL-TM v3.0, 3 May 2024), version checked against the document's own front matter. The page at this URL was not opened. Licence terms were not read, so put it in your own words and do not quote it.

    V52 opened the actual publisher PDF7 November 2026: version 3.0,3 May 2024 front matter,§§0.5–0.11, all substantivechapters 1–3/48 learning objectives and selectedreferences throughprintedp 71. Not every appendix or cited book. Earlier mirror access above is historical. Copyright does not establish unrestricted commercial figure copying.

Deepest material on this page: L4 — Standards & sources. Where a topic stops short of implementation depth, that is a deliberate coverage decision, not an oversight — see coverage.