LAB 1 OF 31

Walk the test process

Step through the test process from a release goal to a test summary, then play the paths where something goes differently.

The diagram

The test process — swimlane diagram — path diagram1. Release goals and risks (Nina (owner) to Mei (test lead)); 2. Plan the testing (Mei (test lead)); 3. Plan and scope (Mei (test lead) to Tom (tester)); 4. Analyse what to test (Tom (tester)); 5. Design test cases (Tom (tester)); 6. Set up data and place (Tom (tester)); 7. Run the tests (Tom (tester)); 8. Report defects (Tom (tester) to Leo (developer)); 9. Fix to retest (Leo (developer) to Tom (tester)); 10. Retest and recheck (Tom (tester)); 11. Results and coverage (Tom (tester) to Mei (test lead)); 12. Test summary (Mei (test lead) to Nina (owner)); 13. Close and learn (Mei (test lead))1. Release goals and risks2. Plan thetesting3. Plan and scope4. Analyse what totest5. Design testcases6. Set up data andplace7. Run the tests8. Report defects9. Fix to retest10. Retest andrecheck11. Results and coverage12. Test summary13. Close andlearn
STEP 1 / 13MESSAGE

Start from what matters

Nina (owner) → Mei (test lead)

Nina tells Mei what the release is for and what would hurt most if it broke. Testing effort is guided by risk, not by habit.

Read the lesson: Risk-based test planning

Checks

  • The release goal is one sentence
  • The worst outcomes are named

Step 1 of 13: Start from what matters

One main path and seven alternative branches are drawn. Real test work repeats and overlaps: planning continues while tests run, progress is checked against the plan all along, and fixes bring more retesting.

Full step-by-step text (works without JavaScript)
  1. 01Hand-over
    Start from what mattersNina (owner) → Mei (test lead)

    Nina tells Mei what the release is for and what would hurt most if it broke. Testing effort is guided by risk, not by habit.

    Read the lesson: Risk-based test planning

  2. 02Work
    Plan the testingMei (test lead)

    Mei decides what will be tested, by whom, how deeply and by when. A plan is a set of choices written down.

    Read the lesson: The test process, step by step

  3. 03Hand-over
    Share the planMei (test lead) → Tom (tester)

    Mei gives Tom the scope and the order of work. Tom now knows which parts of Daily List matter most.

  4. 04Work
    Work out what to testTom (tester)

    Tom reads the requirements and the stories. Each unclear sentence is a question, which is cheaper to ask now than after release.

    Read the lesson: Reviews and static testing

  5. 05Work
    Design the test casesTom (tester)

    Tom turns each idea into test cases with steps and expected results. Boundary values and partitions help him choose few, strong cases.

    Read the lesson: Writing test conditions and test cases

  6. 06Work
    Get ready to runTom (tester)

    Tom prepares the test accounts, the test data and a safe copy of the app. Nothing is run on real users' lists.

  7. 07Check
    Run the testsTom (tester)

    Tom follows each test case and records what happened. Record passed, failed, blocked and not-run work distinctly. An anomaly is a lead to investigate; its cause may involve the test, data or environment rather than only the app.

    Read the lesson: Exploratory testing and error guessing

  8. 08Check
    Report what failedTom (tester) → Leo (developer)

    Tom writes a defect report Leo can act on: what he did, what he expected and what happened instead.

    Read the lesson: Writing a defect report: severity and priority

  9. 09Hand-over
    Fix and hand backLeo (developer) → Tom (tester)

    Leo supplies a corrected version. Tom checks the fix and assesses affected behavior and dependencies for regression testing.

  10. 10Check
    Confirm the fix and assess regressionTom (tester)

    Tom repeats the failing case and any additional confirmation cases needed for the fix. Regression testing uses impact and risk to check for unwanted effects in affected behavior or dependencies. Passing those checks is evidence for the tried conditions, not proof nothing else broke.

  11. 11Record
    Gather the resultsTom (tester) → Mei (test lead)

    Tom tells Mei what was run, what passed and what is still open. Coverage says how much of the requirements the tests have reached. Progress says how much of the plan was run.

  12. 12Record
    Give the decision-makers the pictureMei (test lead) → Nina (owner)

    Mei writes a short summary for Nina in plain words. It shows the risks that remain, so Nina can decide on a release.

  13. 13Work
    Close and keep the lessonsMei (test lead)

    Mei saves the useful tests and notes what to do better next time. Testing ends with what the team learned.

SYNTHETIC / TRAINING ONLY. The Daily List app and the people in it are made up, and every number is a teaching figure.

What this shows

The test process: planning, analysis, design, running, reporting and closing are separate jobs with different outputs.

Read the lessons

NEXT LAB: FOLLOW A BUG →