Follow a bug
Follow one defect from a failed check to a closed report, then play the paths where it cannot be repeated, is not a bug, is deferred, or comes back.
The diagram
A check fails
Tom (tester)
Tom adds a task with a due date in another time zone, and the due date shows the wrong day. Something differs from what was expected.
Read the lesson: Writing a defect report: severity and priority
Checks
- The expected result is written before the run
- The actual result is noted exactly
Step 1 of 8: A check fails
Teams name the states of a defect differently. This path uses plain words: found, reported, triaged, fixed, checked and closed. ISTQB does not fix a list of states, so each team sets its own. Many add reopened, deferred, rejected and duplicate.
Full step-by-step text (works without JavaScript)
- 01WorkA check failsTom (tester)
Tom adds a task with a due date in another time zone, and the due date shows the wrong day. Something differs from what was expected.
Read the lesson: Writing a defect report: severity and priority
- 02WorkPreserve evidence before reportingTom (tester)
Tom preserves the original observation and setup, then attempts repetition and records the steps and repeat rate. An intermittent failure can still be reported with known evidence and uncertainty.
Read the lesson: Reproducing a bug every time
- 04WorkDecide how serious it isMei (test lead)
Mei, Leo and Nina look at it together. Severity says how bad the effect is. Priority says how soon it should be fixed.
Read the lesson: Defect triage
- 05WorkLeo fixes the causeLeo (developer)
Leo finds why the due date moves, fixes the cause and writes a small check so it cannot return unseen.
- 07WorkRetest, then check nearbyTom (tester)
Tom repeats the exact steps and the date is right. This is retesting, also called confirmation testing. He also runs regression checks selected from the change impact, including connected components where relevant. This is regression testing.
Read the lesson: Retesting a fixed bug
- 08WorkClose the defectTom (tester)
Tom closes it with a note of the version where it was checked. A defect closed as fixed is one the team has checked, not one it hopes is gone. Reports closed as works as designed or duplicate carry a reason instead.
SYNTHETIC / TRAINING ONLY. The Daily List app and the people in it are made up, and every number is a teaching figure.
What this shows
The defect life cycle: report, triage, fix and retest are separate steps, and a closed defect is one that was checked again.