TOPIC 01/2914 MINNOT STARTED

Turned away at the front door: MT101 instructions Bank Alfa will not take

Nine ways an MT101 request is refused or stopped before the bank accepts it, and which message answers which.

L1–L4 are part of the Pro pass

L0 Explain simply

Use case: Asha Traders asks Bank Alfa to pay a supplier by MT101, and the request is turned away. Where did it stop, and has any money moved?

Asha Traders sends payment requests to Bank Alfa as an MT101, a . is short for message type, and 101 is the number of this one. It travels on the Swift network, a network banks use to send each other messages. SYNTHETIC / TRAINING ONLY: Asha Traders, Bank Alfa, Northstar Components and Maya Chen are fictional.

An MT101 is a request. It is not a payment. Between the request and any money moving, Bank Alfa checks it at its front door. This lesson covers the nine ways that check can say no, or the request can be stopped.

The first rule is the same for a request turned away before Bank Alfa accepts it. It has moved no money. Asha's account has not been debited for it, and no other bank has been asked to act. One of the nine paths, a change made after approval, is the exception. If Bank Alfa has already debited the account, money may have moved, and the later lifecycle lessons take over.

A refusal is the control working. It is a calm outcome. The work is to find out which door said no, because each door has a different fix and a different person who owns it.

Here is the question to hold. Asha's screen says the message was sent. Does that mean Bank Alfa took it? Not yet. The network may have accepted the message, and Bank Alfa may still decline it. Those are two separate answers.

Maya Chen is a payments operations analyst at Bank Alfa. She reads both answers before she tells Asha anything.

Check yourself. The network accepted Asha’s MT101, but an hour later the supplier is unpaid. Does that prove Bank Alfa accepted the business request? No. A (Swift's store-and-forward message service) (acknowledgement) records network acceptance following its validation; it proves neither delivery to the business application nor execution, settlement or beneficiary credit.

PLAIN WORDS · 1 in this section
acknowledgement
a reply saying a message was received or accepted

PICTURE IT

A parcel counter with three windows

Picture Asha Traders carrying a parcel to a counter that has three windows in a row. The parcel holds a note that asks the counter to pay a supplier on Asha's behalf. The note is a request. It is not the payment.

At the first window a clerk looks only at the label. Is the writing readable and is every box filled in? If not, the clerk hands the parcel straight back with a short reason. Nothing went further.

At the second window a different clerk looks at a list. Is the sender on the list for this account? If not, the clerk keeps the note and sends a written reply saying no. The parcel was perfectly neat and still went nowhere.

At the third window a clerk checks the till and the daily limit. Is there enough in the till, and is this note inside the agreed limit and approvals? A full till does not help if the limit is passed.

Two more turns can happen. A second copy of the same note arrives, and the clerk must find the first before deciding. Or Asha takes a note back before the clerk has touched it. (SYNTHETIC / TRAINING ONLY: the people and places in this picture are invented.)

THE REAL JOB The network and the bank check a , an MT101, in stages; A bad request is stopped before any money moves.

  1. Asha Traders sends the MT101
  2. The network reads it and answers
  3. Bank Alfa checks the sender and the account
  4. Bank Alfa checks funds, limit and approval
  5. Bank Alfa replies, or the request goes on
Where an MT101 can be stopped

HOW THE PICTURE MAPS

How each part of the picture matches the payment
In the pictureIn the payment
The customer who carries the note to the counterAsha Traders, who sends the MT101Who: Asha Traders
The counter that holds the account and decidesBank Alfa, the bank that holds the account and decidesWho: Bank Alfa
The first window, which checks the label onlyThe network door: it returns an acknowledgement or a refusal called a NAK (negative acknowledgement)
The second window with the list of sendersThe bank door: it checks it agreed to take requests from this sender
The written reply that says noThe MT195 or MT199 rejection notice
The third window with the till and the limitThe money door: the bank's own records of funds, limits and approvals
A second copy of the same noteA duplicate request: the bank compares sender, reference and part number
The clerk who reads the replies and tells AshaMaya Chen, who reads both the network answer and the bank answerWho: Maya Chen

WHERE THIS PICTURE STOPS

  • The counter keeps the parcel in view. Real banks send replies as messages, and a reply that nobody matches to its request is as good as no reply.
  • A real bank may check in a different order or all at once. The three windows are a teaching order.
  • The picture cannot show what a bank does with a partly arrived or changed request. No public source fixes those rules, so each bank's agreement decides.

HOOK

A good acknowledgement is not the bank saying yes.

TELL A FRIEND

An MT101 is only a request, and it can be stopped at the network, at the bank, or at the money check. A good acknowledgement from the network does not mean the bank said yes.

OFTEN MIXED UP WITH Turned away at the front door: instructions Bank Alfa will not take. That lesson covers refusals of the newer ISO 20022 customer file. This one covers the older MT101 request and its replies.

CURRENT AS CHECKED

3 FIGURES
  • Swift CBPR+ FI-to-FI payment instructions

    Swift coexistence for in-scope -to-FI payment instructions ended on 22 November 2025; that deadline did not retire every MT reporting, initiation, investigation or correspondence message.

    CHECKED 2026-10-11RECHECK BY 2027-01-05

    Sources & standards — 2 sources
    1. Official requirement

      ISO 20022 Standards (Swift ISO 20022 adoption programme) ↗ — Swift · End of coexistence — 22 November 2025

      Describes current CBPR+ adoption, the 22 November 2025 end of coexistence for in-scope FI-to-FI payment instructions, later migration work and the structured-address milestone. That milestone was previously due in November 2026 and has since been deferred (see swift-sr2026-controlled-extension-2026). · Checked 2026-07-18

      Do not generalise the payment-instruction deadline to every FIN message. Swift publishes differentiated NAK, contingency-conversion, reporting, initiation and exceptions-and-investigations treatment.

    2. Official requirementJune 2026 edition read in full; September 2026 edition seen as search excerpts only

      CBPR+ roadmap beyond November 2025 ↗ — Swift · Message-specific roadmap beyond November 2025

      Current roadmap for post-coexistence Cross-Border Payments and Reporting Plus (CBPR+) work, including contingency processing, payment initiation relay, reporting and exceptions-and-investigations migration milestones.

      Cited on the MT999 record for the E&I pairing: free-format MT199 (free-format message) / MT299 (free-format message) / MT999 used for exceptions and investigations migrate to camt.110 (investigation request) and camt.111 (investigation response). Non-E&I MT199/MT299 use cases are a different row and go to admi.024 (notification of correspondence).

      Also cited for the cheque row: camt.107 (cheque presentment notification), camt.108 and camt.109 (cheque cancellation or stop report) map to MT (message type) 110, MT 111 and MT 112, and cheques continue MT and ISO coexistence until further notice (search excerpt of swift-resource/252463, page not opened). The coexistence statement can change between dated editions, so no current fact is registered and lessons tell the reader to read the current edition. · Checked 2026-10-04

      Roadmap dates and message treatment are service-specific and can change. Recheck the current document before using a milestone in delivery planning.

      The June 2026 download (swift.com/swift-resource/252463/download) is the same programme this document-centre page points at. It lists, under exceptions and investigations, MT199 / MT299 / MT999 as retired for E&I in favour of camt.110 and camt.111, and it separately sends non-E&I MT199/MT299 use cases to admi.024 by November 2027. That pairing is what the MT999 record's ISO counterpart note now cites. The document-centre URL stays the registered address because it is the publisher's standing location for the current file.

      Re-checked on 2026-10-04 by web search. The roadmap now has a September 2026 edition at swift.com/swift-resource/252463/download, and only search excerpts of it were seen; the page was not opened.

      The excerpts said the exceptions and investigations changes were deferred, and that the mandate to receive a camt.110 would come with the deferred part of Standards Release 2026. They also said the roadmap's dates might be out of date until the scope and timeline of that release, and of Standards Release 2027, are confirmed. Other lines of the same roadmap still gave November 2026 for receiving a camt.110, so the excerpts disagree with each other. The fact swift-exceptions-investigations-migration-milestones records both readings.

  • Swift post-November-2025 contingency processing

    After coexistence, treatment differs by : some instructions are NAKed and selected messages can enter temporary , chargeable since 1 January 2026. This is not continued normal MT-MX coexistence.

    CHECKED 2026-10-11RECHECK BY 2027-01-05

    Sources & standards — 1 source
    1. Official requirementJune 2026 edition read in full; September 2026 edition seen as search excerpts only

      CBPR+ roadmap beyond November 2025 ↗ — Swift · Post-coexistence NAK and contingency-conversion treatment

      Current roadmap for post-coexistence Cross-Border Payments and Reporting Plus (CBPR+) work, including contingency processing, payment initiation relay, reporting and exceptions-and-investigations migration milestones.

      Cited on the MT999 record for the E&I pairing: free-format MT199 (free-format message) / MT299 (free-format message) / MT999 used for exceptions and investigations migrate to camt.110 (investigation request) and camt.111 (investigation response). Non-E&I MT199/MT299 use cases are a different row and go to admi.024 (notification of correspondence).

      Also cited for the cheque row: camt.107 (cheque presentment notification), camt.108 and camt.109 (cheque cancellation or stop report) map to MT (message type) 110, MT 111 and MT 112, and cheques continue MT and ISO coexistence until further notice (search excerpt of swift-resource/252463, page not opened). The coexistence statement can change between dated editions, so no current fact is registered and lessons tell the reader to read the current edition. · Checked 2026-10-04

      Roadmap dates and message treatment are service-specific and can change. Recheck the current document before using a milestone in delivery planning.

      The June 2026 download (swift.com/swift-resource/252463/download) is the same programme this document-centre page points at. It lists, under exceptions and investigations, MT199 / MT299 / MT999 as retired for E&I in favour of camt.110 and camt.111, and it separately sends non-E&I MT199/MT299 use cases to admi.024 by November 2027. That pairing is what the MT999 record's ISO counterpart note now cites. The document-centre URL stays the registered address because it is the publisher's standing location for the current file.

      Re-checked on 2026-10-04 by web search. The roadmap now has a September 2026 edition at swift.com/swift-resource/252463/download, and only search excerpts of it were seen; the page was not opened.

      The excerpts said the exceptions and investigations changes were deferred, and that the mandate to receive a camt.110 would come with the deferred part of Standards Release 2026. They also said the roadmap's dates might be out of date until the scope and timeline of that release, and of Standards Release 2027, are confirmed. Other lines of the same roadmap still gave November 2026 for receiving a camt.110, so the excerpts disagree with each other. The fact swift-exceptions-investigations-migration-milestones records both readings.

  • Swift FIN interbank MT101 relay

    Swift's roadmap was due to discontinue the interbank (request for transfer) relay over (Swift's messaging network) by 14 November 2026. A CBPR+ (Cross-Border Payments and Reporting Plus) pain.001 relay was to replace it.

    On 27 August 2026 Swift deferred that migration, alongside the rest of that year's payments changes, with no replacement date set. Swift has said an update is to follow; a bank page gives December 2026. Once coexistence ends, a single MT101 goes through chargeable and a multiple MT101 is NAKed.

    The company-to-bank MT101 is a separate question. Corporates on (Swift's service for corporates) or a were never in that FIN deadline.

    CHECKED 2026-08-27RECHECK BY 2027-01-05

    Sources & standards — 2 sources
    1. Official requirement

      Swift accepts community request to extend structured address migration for ISO 20022 payment messages ↗ — Swift · Deferral of SR2026 payments changes, including the interbank MT101 relay retirement, and the promised update by December 2026

      Swift's own announcement of 27 August 2026, updated on 21 September 2026, for the controlled extension of Standards Release 2026. Swift deferred the payments changes that had been planned for November 2026. The structured-address requirement remains on a separately managed timetable. The 21 September update sets 12 June 2027 for the deferred SR2026 package covering all MT messages except Category 1, ISO 20022 securities and funds messages, Tracker messages, and exceptions-and-investigations messages. This source therefore supersedes older November 2026 dates for SR2026 E&I message changes. · Checked 2026-11-12

      Publisher page opened again on 5 November 2026. The 27 August announcement and 21 September update remain visible. Deferred SR2026 message changes include E&I and go live on 12 June 2027. It does not set 12 June 2027 as the new structured-address deadline. The explicit camt.110 receive wording is on the separate translation FAQ; compare the older Case Management page before asserting a date. No closed Knowledge Centre detail was inferred.

      Re-checked 12 November 2026: no November 2026 SR2026 activation; deferred non-payments package still listed for 12 June 2027; payments changes still deferred with December 2026 update horizon.

    2. Official requirement

      Swift Standards MT (annual standards releases) ↗ — Swift · The original requirement now under deferral: interbank MT101 relay retirement date

      Defines the MT message standards (including MT101, MT103, MT202/202 COV, and the MT9xx statement messages) exchanged over the Swift FIN network, maintained through annual standards releases. · Checked 2026-11-12

      Full field-level specifications live in the Swift Knowledge Centre User Handbook behind a swift.com login. Coexistence for in-scope FI-to-FI payment instructions ended on 22 November 2025, but treatment differs by MT: some instructions are NAKed and selected messages can enter temporary, chargeable contingency conversion. Reporting, initiation, investigations and correspondence follow separate roadmaps.

      Re-checked on 2026-10-04 by web search for the schedule of Standards Release 2026. Only search excerpts of the Standards Releases page were seen; the page was not opened. They said the deferred part of the release, which holds MT messages outside category 1, ISO 20022 securities and funds messages, tracker messages and exceptions and investigations messages, now has a date of 12 June 2027. They said the first target was the first quarter of 2027, and that the later date follows industry feedback about other change work, including the European move to T+1 settlement. An audit note in docs/research dated 29 September 2026 recorded the same date from the same page.

      Re-checked 12 November 2026 via Swift Standards Releases schedule: SR2025 remains the in-force annual MT release pending the deferred SR2026 package.

SEE THE PAYMENT MOVE

PICTURE THE JOURNEY

A frame shop, a glass factory and a ledger hall with one card per officeOpen to read the picture, how it matches the payment and where it stops.

PICTURE IT

A frame shop, a glass factory and a ledger hall with one card per office

Picture a frame-shop owner who must pay a glass factory in another country for a load of glass. She keeps her money at her local cashier office. The glass factory keeps its money at a different cashier office abroad. The two offices have no direct dealings. Each keeps a balance card at a ledger hall, and a relay office carries notes between them.

She signs an order slip and hands it to her cashier office. The slip is only a request. The cashier checks that she may order and that her money is there. It also checks the and that no name is on a banned list. If the slip cannot be carried out, she hears in whatever way she and the office agreed. Otherwise the office takes the amount from her account and gives her a small slip that says one amount has left.

The office then writes the payment letter and hands it to the relay office. The relay office checks that the letter follows the printed form, keeps it safe until the next stop is ready and passes it on. It never touches a balance card. The ledger hall reads the letter and checks the names again for itself. Then it lowers her office's card and raises the glass factory's office's card. That entry is the moment the amount changes hands. The hall sends the glass factory's office a credit slip, and the payment letter follows through the relay office.

The glass factory's office checks the letter, matches it to the credit slip and adds the amount to the glass factory's account. Through the day the frame-shop owner receives a balance sheet and a list of entries, and at close a day statement. The ledger hall also sends each cashier office a copy of its own card, and the office compares that copy with its own book.

Several other turns are possible. If the ledger hall keeps a small handling fee, less glass money arrives. If the hall refuses the letter before it makes any entry, her office puts the amount back in her account. If the glass factory's office finds the account closed, it sends the amount back as a new payment the other way. If an office needs more detail, it posts a query note and waits for the reply. If the two copies of a card disagree, a clerk checks whether an entry is merely late or truly missing. If she asks for the amount back after the glass factory is paid, that is only a request, and the glass factory's office can refuse. (SYNTHETIC / TRAINING ONLY: the frame-shop owner and the glass factory are invented.)

THE REAL JOB A company pays a supplier abroad through its bank in the older Swift message format, with confirmations, reports, queries and returns.

HOW THE PICTURE MAPS

How each part of the picture matches the payment
In the pictureIn the payment
The frame-shop owner signs an order slip for her cashier officeAsha Traders asks Bank Alfa to pay with the request message MT101Who: Asha Traders
The cashier checks her right to order, her money, the cut-off and the namesBank Alfa validates the authority, funds, cut-off, routing and screeningWho: Bank Alfa
The office takes the amount and gives her a small slipBank Alfa debits Asha Traders; where agreed, MT900 confirms that one debitWho: Bank Alfa
The relay office checks the printed form, keeps the letter safe, passes it onSwift FIN, the message network, checks the format and forwards messages; it holds no account
The payment letter that her office posts to the ledger hallThe customer payment message MT103 is the instruction, not the money
The ledger hall reads the letter and checks the names for itselfMeridian Bank validates and screens the payment for itselfWho: Meridian Bank
The hall lowers one office's card and raises the other'sBook transfer: Meridian Bank debits Bank Alfa's account and credits Nordbank's accountWho: Meridian Bank
A credit slip goes to the glass factory's officeMT910 tells Nordbank that its account at Meridian Bank was credited
The glass factory's office matches the letter to the slip, then creditsNordbank validates, screens and matches the payment before it pays its customerWho: Nordbank
The glass factory's account goes upNorthstar Components, the supplier, is credited by NordbankWho: Northstar Components
A balance sheet and a list of entries by day, a statement at closeMT941 gives balances, MT942 lists daytime entries and MT940 is the day statement
The owner ticks each statement line against her own order slipAsha Traders matches the MT940 entry to its own request, MT101
The hall sends each office a copy of its own cardMT950 reports the entries on Bank Alfa's account at Meridian BankWho: Meridian Bank
A clerk lays two cards side by side and finds an entry on only oneMaya Chen compares Bank Alfa's books with the MT950; a lone entry is a breakWho: Maya Chen
An entry written today on one card and tomorrow on the otherA timing difference clears itself; an unmatched entry gets a query, MT199
The cashier cannot carry out the slip and tells her in the agreed wayA rejected request: no MT103 is sent and funds stay with Asha Traders
The hall keeps a small handling fee as the letter passesShared charges: Meridian Bank takes off a fee, so the supplier receives lessWho: Meridian Bank
The hall refuses the letter before it makes any entryREJT: no value is booked, so Bank Alfa restores the customer balance
The glass factory's office finds the account closed and sends the amount backRETN: Nordbank returns settled funds as a second payment the other wayWho: Nordbank
An office posts a query note, and the reply comes backMT195 asks, MT196 answers; MT199 is the free-text version
The owner asks her office to get the paid amount backBank Alfa sends MT192, a cancellation request; it asks and reverses nothingWho: Bank Alfa
The glass factory's office agrees to hand it back, or refusesMT196 answers: CNCL accepted, with a return to follow, or RJCR refused

WHERE THIS PICTURE STOPS

  • In the picture the owner could ask her office to get the amount back. In the journey that is a cancellation request, MT192. It only asks. The beneficiary's bank can refuse it, and the first settlement stands.
  • The slips and sheets in the picture look like proof that the glass factory was paid. They are not. MT900 confirms one debit, and MT940 lists entries on Asha Traders' own account. Only the credit at Nordbank shows the supplier was paid.
  • The ledger hall in the picture is one keeper with a card for each office. This journey settles on one correspondent's books. Other routes use more banks or a shared payment system, and the picture cannot show which.
  • The picture does not say how current this route is. This journey is the older Swift message format, and a new build does the same job in ISO 20022.
  • The handling fee in the picture is small and illustrative. In the journey the charge option, such as SHA for shared, decides who bears each bank's fee. The message trail is the only record of what was taken.
  • The cashier in the picture tells the owner of a failed slip in an agreed way. A real corporate service is agreed bank by bank, so how a failure reaches the customer varies. Swift's rules have the bank send a rejection advice, normally an MT195 (a query), though an MT199 (a free-format message) is allowed. The ISO 20022 journey uses the structured pain.002 status report.

HOOK

Messages ask, report and query. One ledger entry settles.

REMEMBER IT THIS WAY

A chunk: a long list grouped so it is easier to hold.

Group the account reports by what they hold: MT941 balances, MT942 daytime entries and MT940 the day statement.

What each part of the trick stands for
In the trickWhat it stands for
MT941gives balances
MT942lists daytime entries
MT940is the day statement

TELL A FRIEND

In the older Swift message format, one payment brings a request, the payment message, confirmations, reports and queries. The between banks is what settles it.

OFTEN MIXED UP WITH What the network says back (ACK, NAK). That topic teaches the network's accepted-or-refused answer to one message. This journey shows the bank answers, such as debit, credit, reject, return and statement, which arrive as other messages.

MESSAGES INVOLVED

PRACTISE AND KEEP

IMPLEMENTATION RESOURCES

14 RESOURCES

EVIDENCE AT ARM'S REACH

Apply the base message definition first, then the scheme or infrastructure profile that governs this topic.

An XSD checks XML structure. A usage guideline adds profile rules, conditional fields, code restrictions, and business controls. XSD-valid does not mean scheme-compliant.

Teaching sampleIllustrative; no scheme profile checked

FIN acknowledgement (accepted) — raw FIN

PRO PASS
Teaching sampleIllustrative; no scheme profile checked

FIN acknowledgement (refused) — raw FIN

PRO PASS
Teaching sampleIllustrative; no scheme profile checked

MT101 request for transfer — raw FIN

PRO PASS
Teaching sampleIllustrative; no scheme profile checked

MT199 free-format payment message — raw FIN

PRO PASS
Lifecycle packIllustrative; no scheme profile checked

MT legacy and migration lifecycle — ZIP pack

PRO PASS
MappingCBPR+

MT101 → pain.001 implementation mapping

PRO PASS
MappingCBPR+

MT199 query → camt.110 implementation mapping

PRO PASS
MappingCBPR+

MT199 answer → camt.111 implementation mapping

PRO PASS
Field matrixSwift MT

MT101 field matrix

PRO PASS
Field matrixSwift MT

MT199 field matrix

PRO PASS
Field matrixSwift MT

ACK / NAK field matrix

PRO PASS
Field matrixSwift MT

NAK field matrix

PRO PASS
Migration notesCBPR+

MT to MX migration notes

PRO PASS
Sources for this topic — 8 sources
  1. Official requirement

    Swift Standards MT (annual standards releases) ↗ — Swift · Category 1 MT101 Request for Transfer; FIN system messages, acknowledgements and error codes; handbook behind a swift.com login, not opened

    Defines the MT message standards (including MT101, MT103, MT202/202 COV, and the MT9xx statement messages) exchanged over the Swift FIN network, maintained through annual standards releases. · Checked 2026-11-12

    Full field-level specifications live in the Swift Knowledge Centre User Handbook behind a swift.com login. Coexistence for in-scope FI-to-FI payment instructions ended on 22 November 2025, but treatment differs by MT: some instructions are NAKed and selected messages can enter temporary, chargeable contingency conversion. Reporting, initiation, investigations and correspondence follow separate roadmaps.

    Re-checked on 2026-10-04 by web search for the schedule of Standards Release 2026. Only search excerpts of the Standards Releases page were seen; the page was not opened. They said the deferred part of the release, which holds MT messages outside category 1, ISO 20022 securities and funds messages, tracker messages and exceptions and investigations messages, now has a date of 12 June 2027. They said the first target was the first quarter of 2027, and that the later date follows industry feedback about other change work, including the European move to T+1 settlement. An audit note in docs/research dated 29 September 2026 recorded the same date from the same page.

    Re-checked 12 November 2026 via Swift Standards Releases schedule: SR2025 remains the in-force annual MT release pending the deferred SR2026 package.

  2. Implementation-specific

    PostFinance: guide to the MT101 request (460.47) ↗ — PostFinance · One bank's manual: a payment it cannot execute is rejected and reported to the sender in an MT195 (search excerpt, page not opened)

    One bank's guide to the MT101 request: a same-day order is cancelled at once when the debit account lacks cover, and a payment it cannot execute is rejected and reported to the sender in a query message (MT195). · Checked 2026-10-11

    One bank's practice, not a scheme rule. Known only from a web-search excerpt; the page was not opened.

  3. Implementation-specific

    Australia and New Zealand Banking Group: customer guide to the MT101 request format ↗ — Australia and New Zealand Banking Group · One bank's format guide: an MT101 is rejected when a possible duplicate payment is found; messages failing network validation are rejected by Swift (search excerpt, page not opened)

    One bank's guide to the MT101 request. Messages that fail network validation are rejected by Swift. A payment is flagged as a possible duplicate when another payment within six calendar days matches on funding account, beneficiary account and name, amount, currency and first remittance line. · Checked 2026-10-11

    One bank's rule, not a scheme rule. Known only from a web-search excerpt; the page was not opened.

  4. Scheme-specific rule

    Swift: request for transfer service level rules ↗ — Swift · The executing bank's rejection or suspension advice: an MT195 or an MT199 (search excerpt, page not opened; an older Swift document, so the current text should be checked)

    Swift's service level rules for the request for transfer. The executing bank sends a rejection or suspension advice, normally as an MT195, and an MT199 is allowed instead. A reject is made as soon as possible, with no fixed deadline. · Checked 2026-10-11

    An older Swift document that says its annex applies until the rules are folded into the Swift Standards volumes, so the current text should be checked. Known only from a web-search excerpt; the page was not opened.

  5. Implementation-specific

    Oracle Banking Payments: how its product handles Swift message types ↗ — Oracle · One product's documentation: incoming MT101 duplicate check on host, sender, field 20 and the 28D index and total; a match goes to a business override queue (search excerpt, page not opened)

    A core banking vendor's guide saying its product runs a duplicate check on an incoming MT101 request, using the sender, the reference and the message index and total, then sends flagged items to a manual queue. · Checked 2026-10-11

    A vendor guide describes one product, not the standard. Known only from a web-search excerpt; the page was not opened.

  6. Official requirementJune 2026 edition read in full; September 2026 edition seen as search excerpts only

    CBPR+ roadmap beyond November 2025 ↗ — Swift · Post-coexistence NAK and contingency-conversion treatment, claimed through the facts register

    Current roadmap for post-coexistence Cross-Border Payments and Reporting Plus (CBPR+) work, including contingency processing, payment initiation relay, reporting and exceptions-and-investigations migration milestones.

    Cited on the MT999 record for the E&I pairing: free-format MT199 (free-format message) / MT299 (free-format message) / MT999 used for exceptions and investigations migrate to camt.110 (investigation request) and camt.111 (investigation response). Non-E&I MT199/MT299 use cases are a different row and go to admi.024 (notification of correspondence).

    Also cited for the cheque row: camt.107 (cheque presentment notification), camt.108 and camt.109 (cheque cancellation or stop report) map to MT (message type) 110, MT 111 and MT 112, and cheques continue MT and ISO coexistence until further notice (search excerpt of swift-resource/252463, page not opened). The coexistence statement can change between dated editions, so no current fact is registered and lessons tell the reader to read the current edition. · Checked 2026-10-04

    Roadmap dates and message treatment are service-specific and can change. Recheck the current document before using a milestone in delivery planning.

    The June 2026 download (swift.com/swift-resource/252463/download) is the same programme this document-centre page points at. It lists, under exceptions and investigations, MT199 / MT299 / MT999 as retired for E&I in favour of camt.110 and camt.111, and it separately sends non-E&I MT199/MT299 use cases to admi.024 by November 2027. That pairing is what the MT999 record's ISO counterpart note now cites. The document-centre URL stays the registered address because it is the publisher's standing location for the current file.

    Re-checked on 2026-10-04 by web search. The roadmap now has a September 2026 edition at swift.com/swift-resource/252463/download, and only search excerpts of it were seen; the page was not opened.

    The excerpts said the exceptions and investigations changes were deferred, and that the mandate to receive a camt.110 would come with the deferred part of Standards Release 2026. They also said the roadmap's dates might be out of date until the scope and timeline of that release, and of Standards Release 2027, are confirmed. Other lines of the same roadmap still gave November 2026 for receiving a camt.110, so the excerpts disagree with each other. The fact swift-exceptions-investigations-migration-milestones records both readings.

  7. Market practice

    Payments Market Practice Group (PMPG) Best Practice Guidance for the Return of Funds and Rejects of Payments ↗ — Swift / Payments Market Practice Group · Return of Funds and Rejects May 2025, operative pp3–25 read6November2026: settlement-method/leg scope, actual original references, settled-return handling and partial returns; Scenario4 heading/body ambiguity disclosed.

    Distinguishes rejection of an unsettled instruction from returning settled funds; serial and cover examples and settlement-method context. · Checked 2026-09-28

    Public PDF opened through web search. Applied per interbank leg, not as a single status for the entire customer journey. Bank service rules still govern permitted messages and responses.

  8. Simplified educational illustration

    Payments Signal editorial teaching models — Payments Signal · The nine MT101 front-door paths and the three-door order used to sort them

    This site's own simplified teaching models. · Checked 2026-07-12

    What this simplifies: The nine paths are this lesson's own labels, not message codes. Five of them (the network refusal, no authority, the bank's rejection, the repeated request and low funds) are branches of this site's MT (message type) corporate lifecycle flow. The other four are teaching labels only. The three doors are a teaching order, not a bank's order of checks. Rejection-notice shape, duplicate checks, part handling, amendment, cancellation, funds and limit replies are set in each bank's agreement; where no public source fixes a rule, none is given.

    Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.

Deepest material on this page: L4 — Standards & sources. Where a topic stops short of implementation depth, that is a deliberate coverage decision, not an oversight — see coverage.