Agile analysis horizons and rolling-wave planning
Plan analysis at three distances: strategy, initiative and delivery. Learn rolling-wave planning, just-in-time analysis, and how feedback flows between the horizons.
L1–L4 are part of the Pro pass
L0 Explain simply
Analogy: The road trip. Lily plans a long road trip across the country. For the whole country she only marks the big route and the cities. For the next town she chooses the roads. For the next minute she decides the turn. She does not plan every turn of the whole trip today, because roads close and plans change.
Agile work plans the same way. A is how far ahead a plan looks, and how much detail it needs. Agile uses three: strategy, initiative and delivery.
Sam, the for Daily List, works at all three. At the strategy horizon, Nina decides which products and big goals to fund this year. At the initiative horizon, the team works out how to create value, such as a way to share lists. At the delivery horizon, the team builds small pieces and tests them.
Sam varies detail according to the decision, uncertainty and . This is .
The picture has a limit. A trip and a product can both change; business decisions involve different stakeholders, dependencies and commitments.
These are decision horizons, not fixed calendar bands or a management hierarchy. Strategy concerns allocation and direction; initiative concerns value/options for an initiative; delivery concerns creating, testing and learning. Year/quarter/Sprint is this story’s illustration, not the definition.
PICTURE IT
The picture is the one the lesson above opens with. The table below shows how each part of it matches the work.
THE REAL JOB The picture helps a newcomer remember that plans have different detail at different distances.
- Strategy: allocation
- Initiative: value/options
- Delivery: deliver/test/learn
HOW THE PICTURE MAPS
| In the picture | In the work |
|---|---|
| The route across the country | The strategy horizon |
| The roads to the next town | The initiative horizon |
| The turn in the next minute | The delivery horizon |
| Marking only the big route far away | Planning far work loosely |
| Deciding the turn when you reach it | Just-in-time analysis |
WHERE THIS PICTURE STOPS
- Trips and products can both change; commitments still matter.
- A map is fixed, while a plan changes as the team learns.
- One driver decides each turn. A team shares many decisions across horizons.
HOOK
Sketch far, sharpen near, decide at the turn.
REMEMBER IT THIS WAY
A contrast: two neighbours told apart by one test.
Strategy concerns direction/allocation, initiative concerns value/options, and delivery concerns creating/testing/learning. Timing and detail depend on context.
| In the trick | What it stands for |
|---|---|
| Strategy | Organisational direction and resource allocation |
| Initiative | Initiative value, options and dependencies |
| Delivery | Delivering, testing and learning |
TELL A FRIEND
Strategy, initiative and delivery are connected decision horizons. Vary detail with evidence, uncertainty, and commitments.
OFTEN MIXED UP WITH The product backlog. That topic covers the list of work the team keeps. This one covers how much detail each part of the list should carry.
Sources & standards — 5 sources
- Market practice
Agile Extension to the Business Analysis Body of Knowledge (BABOK) Guide (IIBA page) ↗ — International Institute of Business Analysis · IIBA current public AgileExtension page, actual complete Strategy/Initiative/Delivery horizon overview and guide/access description read 7 November 2026 at www.iiba.org. Decisions, value and learning; full member AgileExtension guide not claimed read. No source figure copied.
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail. Actual selected sections above read; prior metadata and wider source-use notes preserved. No full member book or adjacent legacy scheduling rule is implied.
- Market practice
Digital Business Analysis—Embrace Agility (May2019), horizons sections ↗ — International Institute of Business Analysis · IIBA Digital Business Analysis—Embrace Agility, May 2019, actual horizons/relationship/individual-horizon sections printedpp 8–10 read 7 November 2026. Strategy can range 3 months-to-multiple-years; contextual guidelines and two-way feedback/decisions. Other whitepaper sections/full member extension not claimed read; figure rights unverified and not copied.
Actual selected dated source sections read, not a claim of latest standard or entire book review. IIBA PDF SHA1c54959192059568d3d1ef254783d57ed0dea908dcb09dab1b8c2e4c1b9e0ee0; PMI PDF SHAb4ca497cb2bcdb73f92efd76e238030fbef9029179c7c61d67b3523037bf3511. Official figures identified as educational opportunities, but reproduction basis is unverified and no image copied.
- Market practice
Practice Standard for Scheduling, second edition2011 — rolling-wave section ↗ — Project Management Institute · PMI Practice Standard for Scheduling secondedition 2011, actual §2.3.1 printedp 15 plus cover/copyright read 7 November 2026. Near-term detailed planning and future planning packages, periodic advance detail, possible baseline cost/resource commitments;90 days is an example. Adjacent old agile/CPM framing is not adopted as current Scrum rule; no Fig 2-5 copied.
Actual selected dated source sections read, not a claim of latest standard or entire book review. IIBA PDF SHA1c54959192059568d3d1ef254783d57ed0dea908dcb09dab1b8c2e4c1b9e0ee0; PMI PDF SHAb4ca497cb2bcdb73f92efd76e238030fbef9029179c7c61d67b3523037bf3511. Official figures identified as educational opportunities, but reproduction basis is unverified and no image copied.
- Market practice
The Scrum Guide — The Definitive Guide to Scrum: The Rules of the Game (November 2020) ↗ — Ken Schwaber and Jeff Sutherland · Official Scrum Guide November 2020, actual Product Backlog/refinement, Sprint Planning and Sprint Review sections read 7 November 2026: emergent ordered work, ongoing refinement, Done-within-Sprint readiness, possible planning refinement, Developer sizing/selection and feedback. No mandatory 1–2 Sprint buffer, user-story format or universal all-questions-answered rule; no whole-guide read claimed in this pass.
Still current in August 2026. There is no 2025 or 2026 revision of the Guide.
The confusable document is a rename. "Scrum Guide Expansion Pack" (v2025.6) became "Scrum Guide Expanded" (v2026.1, 18 January 2026), published at scrumexpansion.org by Jocham, Coleman and Sutherland. Same URL path, different name, and Jeff Sutherland co-authors both it and the Guide — which is exactly the hook that makes wrong credit plausible. It is not a version of the Scrum Guide.
Nine terms interview answers routinely attribute to Scrum appear zero times in the Guide: story points, velocity, Definition of Ready, sprint zero, user stories, acceptance criteria, grooming, T-shirt sizing, planning poker. So do "estimate" and "estimation".
Two that are usually said to be absent and are present, which is why this paragraph exists: burn-down charts are named once and subordinated — "Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism" — and backlog refinement is defined as "an ongoing activity". What is absent is refinement as an event, and the absent word is "grooming".
The Guide does require Product Backlog items to acquire a size, and puts sizing on the Developers, while naming no unit, scale or technique. It says "accountabilities", not "roles"; five events, not four; never "ceremony".
Read through a mirror, because the publisher's own domain could not be fetched (a reachability gap, not a statement about the publisher). A 403 there is a policy refusal and says nothing about whether the document exists or is reachable elsewhere.
Anyone on an unrestricted network should open the canonical URL above and confirm the section and page numbers cited against it. Every claim drawn from this entry is written so that it can be checked against a numbered page.
Read in full from three independent mirrors that agree byte-for-byte on section structure, on the CC BY-SA 4.0 footer, on word count to within four words, and on all sixteen term-frequency counts above. Edition confirmed as 2020 specifically by zero occurrences of "Development Team" and thirteen of "Product Goal". Actual selected sections above read; prior metadata and wider source-use notes preserved. No full member book or adjacent legacy scheduling rule is implied.
- Simplified educational illustration
Payments Signal editorial teaching models — Payments Signal · Roadtrip/DailyList examples are synthetic. Year/quarter/two-week cadence, onegoal/twothemes/fivestories are local lesson choices; exercise supplies only two near-story items. Commitment status, leadtime and risk need evidence, not universal sentence-only or all-early-detail-is-waste rules.
What this simplifies: Independent educational applications. Decision scope, evidence, forecasts and authorised commitments are distinct; uncertainty may remain and early investigations can be necessary.
Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.
PRACTISE AND KEEP
Sources for this topic — 5 sources
- Market practice
Agile Extension to the Business Analysis Body of Knowledge (BABOK) Guide (IIBA page) ↗ — International Institute of Business Analysis · IIBA current public AgileExtension page, actual complete Strategy/Initiative/Delivery horizon overview and guide/access description read 7 November 2026 at www.iiba.org. Decisions, value and learning; full member AgileExtension guide not claimed read. No source figure copied.
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail. Actual selected sections above read; prior metadata and wider source-use notes preserved. No full member book or adjacent legacy scheduling rule is implied.
- Market practice
Digital Business Analysis—Embrace Agility (May2019), horizons sections ↗ — International Institute of Business Analysis · IIBA Digital Business Analysis—Embrace Agility, May 2019, actual horizons/relationship/individual-horizon sections printedpp 8–10 read 7 November 2026. Strategy can range 3 months-to-multiple-years; contextual guidelines and two-way feedback/decisions. Other whitepaper sections/full member extension not claimed read; figure rights unverified and not copied.
Actual selected dated source sections read, not a claim of latest standard or entire book review. IIBA PDF SHA1c54959192059568d3d1ef254783d57ed0dea908dcb09dab1b8c2e4c1b9e0ee0; PMI PDF SHAb4ca497cb2bcdb73f92efd76e238030fbef9029179c7c61d67b3523037bf3511. Official figures identified as educational opportunities, but reproduction basis is unverified and no image copied.
- Market practice
Practice Standard for Scheduling, second edition2011 — rolling-wave section ↗ — Project Management Institute · PMI Practice Standard for Scheduling secondedition 2011, actual §2.3.1 printedp 15 plus cover/copyright read 7 November 2026. Near-term detailed planning and future planning packages, periodic advance detail, possible baseline cost/resource commitments;90 days is an example. Adjacent old agile/CPM framing is not adopted as current Scrum rule; no Fig 2-5 copied.
Actual selected dated source sections read, not a claim of latest standard or entire book review. IIBA PDF SHA1c54959192059568d3d1ef254783d57ed0dea908dcb09dab1b8c2e4c1b9e0ee0; PMI PDF SHAb4ca497cb2bcdb73f92efd76e238030fbef9029179c7c61d67b3523037bf3511. Official figures identified as educational opportunities, but reproduction basis is unverified and no image copied.
- Market practice
The Scrum Guide — The Definitive Guide to Scrum: The Rules of the Game (November 2020) ↗ — Ken Schwaber and Jeff Sutherland · Official Scrum Guide November 2020, actual Product Backlog/refinement, Sprint Planning and Sprint Review sections read 7 November 2026: emergent ordered work, ongoing refinement, Done-within-Sprint readiness, possible planning refinement, Developer sizing/selection and feedback. No mandatory 1–2 Sprint buffer, user-story format or universal all-questions-answered rule; no whole-guide read claimed in this pass.
Still current in August 2026. There is no 2025 or 2026 revision of the Guide.
The confusable document is a rename. "Scrum Guide Expansion Pack" (v2025.6) became "Scrum Guide Expanded" (v2026.1, 18 January 2026), published at scrumexpansion.org by Jocham, Coleman and Sutherland. Same URL path, different name, and Jeff Sutherland co-authors both it and the Guide — which is exactly the hook that makes wrong credit plausible. It is not a version of the Scrum Guide.
Nine terms interview answers routinely attribute to Scrum appear zero times in the Guide: story points, velocity, Definition of Ready, sprint zero, user stories, acceptance criteria, grooming, T-shirt sizing, planning poker. So do "estimate" and "estimation".
Two that are usually said to be absent and are present, which is why this paragraph exists: burn-down charts are named once and subordinated — "Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism" — and backlog refinement is defined as "an ongoing activity". What is absent is refinement as an event, and the absent word is "grooming".
The Guide does require Product Backlog items to acquire a size, and puts sizing on the Developers, while naming no unit, scale or technique. It says "accountabilities", not "roles"; five events, not four; never "ceremony".
Read through a mirror, because the publisher's own domain could not be fetched (a reachability gap, not a statement about the publisher). A 403 there is a policy refusal and says nothing about whether the document exists or is reachable elsewhere.
Anyone on an unrestricted network should open the canonical URL above and confirm the section and page numbers cited against it. Every claim drawn from this entry is written so that it can be checked against a numbered page.
Read in full from three independent mirrors that agree byte-for-byte on section structure, on the CC BY-SA 4.0 footer, on word count to within four words, and on all sixteen term-frequency counts above. Edition confirmed as 2020 specifically by zero occurrences of "Development Team" and thirteen of "Product Goal". Actual selected sections above read; prior metadata and wider source-use notes preserved. No full member book or adjacent legacy scheduling rule is implied.
- Simplified educational illustration
Payments Signal editorial teaching models — Payments Signal · Roadtrip/DailyList examples are synthetic. Year/quarter/two-week cadence, onegoal/twothemes/fivestories are local lesson choices; exercise supplies only two near-story items. Commitment status, leadtime and risk need evidence, not universal sentence-only or all-early-detail-is-waste rules.
What this simplifies: Independent educational applications. Decision scope, evidence, forecasts and authorised commitments are distinct; uncertainty may remain and early investigations can be necessary.
Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.
Deepest material on this page: L4 — Standards & sources. Where a topic stops short of implementation depth, that is a deliberate coverage decision, not an oversight — see coverage.