Project life cycles and PM artefacts for BAs: charter, schedule, milestones, earned value

Read the project charter, the schedule with its milestones and an earned value report, so you can tell whether the work still matches the need. Written for analysts, not managers.

L1–L4 are part of the Pro pass

L0 Explain simply

Analogy: A holiday plan. Before a trip, a group writes one page. It says where you are going, why, how much you will spend and who decides. Next comes a calendar with checkpoints, such as "at the station by noon". Halfway through, someone asks two questions: how much of the trip is done, and how much money is gone?

A project works the same way. Nina, the for Daily List, wants a calendar connection, so that people see due dates in their own calendar. A runs the project. Sam, the business analyst, makes sure the work still fits what users need.

Three ideas carry this lesson. A is the short note, signed by the sponsor, that says the project may start. The sponsor is the person who backs the project and pays for it. A is the series of stages a project passes through, from first idea to hand-over. Earned value counts the budgeted value of work actually finished; it is not cash received or business benefit. So you can compare it with the plan and with the money spent.

A does not run these papers. Sam reads them, checks them against the real need, and speaks up when they drift.

The limit of the picture: a holiday plan is small and one person decides. A project has a sponsor, a manager and many people, and their wishes can clash.

PLAIN WORDS · 1 in this section
checkpoints
points along the way where a payment is checked

PICTURE IT

The picture is the one the lesson above opens with. The table below shows how each part of it matches the work.

THE REAL JOB The picture helps a newcomer see that a project has a signed start note, a calendar with checkpoints, and a regular check of work done against money spent.

  1. Sign the goal page
  2. Choose the stops
  3. Mark the checkpoints
  4. Count what is done
  5. Compare with money spent
Goal, stops, checkpoints, check

HOW THE PICTURE MAPS

How each part of the picture matches the work
In the pictureIn the work
The one-page goal for the tripThe project charter
The stops on the way, from first to lastThe stages of the project life cycle
Be at the station by noonA milestone in the schedule
How far along the trip you really areEarned value
The money gone so farActual cost

WHERE THIS PICTURE STOPS

  • A holiday plan is small, while a project has a sponsor, a manager and many people.
  • On a trip you can see how far you have come, but finished work in a project has to be agreed.
  • A holiday ends on the day, while a project may change its goal on the way.
  • Earned value is budgeted work progress, not business benefit. SV is in budget units, SPI is not calendar speed, and EAC depends on a stated future-efficiency assumption.

HOOK

Goal page, stops, checkpoints, then done against spent.

REMEMBER IT THIS WAY

A sequence: the real steps, in order.

Earned comes first: take away planned for the schedule gap, then take away actual cost for the cost gap.

What each part of the trick stands for
In the trickWhat it stands for
Earned firstearned value
Take away plannedschedule variance
Take away actual costcost variance

The pattern does not tell you whether the pieces counted as earned really meet the rule for done.

TELL A FRIEND

The charter starts the project, the life cycle is its shape, and compares finished work with the plan and with the money spent.

OFTEN MIXED UP WITH Working with project managers. That topic is about how an analyst and a share the work. This one is about the papers the project manager keeps and what the analyst reads in them.

PRACTISE AND KEEP

Sources for this topic — 18 sources
  1. Market practice

    The charter: selling your project (Project Management Institute library article) ↗ — Project Management Institute · The charter: selling your project (Project Management Institute library article): the charter is a document from the sponsor or initiator that formally approves the project and gives the project manager authority; the sponsor approves it and the project manager often drafts it (search excerpt, page not opened)

    Professional-body article. The charter is described as a document from the sponsor or initiator that formally approves the project and gives the project manager authority over organizational resources. Older papers cite earlier PMBOK editions. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  2. Market practice

    Earned value management tutorial (National Aeronautics and Space Administration, Office of the Chief Financial Officer) ↗ — National Aeronautics and Space Administration (NASA) · Earned value management tutorial (NASA Office of the Chief Financial Officer): schedule variance is earned value minus planned value and cost variance is earned value minus actual cost, with a worked example (search excerpt, page not opened)

    Government tutorial. Gives schedule variance as earned value minus planned value and cost variance as earned value minus actual cost, with a worked example. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  3. Market practice

    Partnering: project manager and business analyst collaboration (Project Management Institute library paper) ↗ — Project Management Institute · Partnering: project manager and business analyst collaboration (Project Management Institute library paper): the business analyst and project manager share work on the business case, charter, scope and requirements; analyst on product scope, manager on project scope (search excerpt, page not opened)

    Professional-body paper. Describes how the business analyst and project manager share work on the business case, the charter, scope and requirements. A 2010 white paper by Project Management Institute and IIBA is described in other excerpts. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  4. Market practice

    Inside the Project Management Body of Knowledge guide, seventh edition: Development Approach and Life Cycle performance domain (Project Management Compass) ↗ — Project Management Compass · Inside PMBOK 7: Development Approach and Life Cycle performance domain (Project Management Compass): a project life cycle is phases from start to end; approaches range from predictive to adaptive, with hybrid between; secondary summary (search excerpt, page not opened)

    Secondary newsletter summary. Describes a project life cycle as phases from start to end, and predictive, iterative, incremental, adaptive and hybrid development approaches. Not the guide itself. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  5. Market practice

    PRINCE2 Agile 2016: tailoring guidance for the PRINCE2 processes (AXELOS publications) ↗ — AXELOS · PRINCE2 Agile 2016: tailoring guidance for the PRINCE2 processes (AXELOS publications): the method is tailored to the project and the processes scale to all project types; justification stays tied to the business case (search excerpt, page not opened)

    Method owner's online guidance. Says the method should be tailored to each project, that the processes scale to all project types, and that all seven themes must be used. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  6. Market practice

    Milestones (Celoxis knowledge base) ↗ — Celoxis · Milestones (Celoxis knowledge base): a milestone is a point in time with no duration, drawn as a diamond; vendor help page (search excerpt, page not opened)

    Vendor help page. A milestone marks a point in time with no duration and is drawn as a diamond on a Gantt chart. Not a standard. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  7. Market practice

    Burndowns considered harmful? (Soliant Consulting blog) ↗ — Soliant Consulting · Burndowns considered harmful? (Soliant Consulting blog): earned value needs a stable baseline, which agile work lacks; practitioner opinion (search excerpt, page not opened)

    Practitioner blog. Discusses the difficulty of using earned value on agile work, because the baseline is fluid. Opinion, not a standard. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  8. Simplified educational illustration

    Payments Signal editorial teaching models — Payments Signal

    This site's own simplified teaching models. · Checked 2026-07-12

    What this simplifies: Daily List, Sam, Nina and the project manager are invented. The actual GAO cost guide supports the earned-value calculations and their limits. Teaching points represent budgeted work, not realised business benefit or days of delay. Real reports, schedules and charters require more context; the full licensed standards were not read.

    Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.

  9. Market practice

    Stage-gate process: how gates and stages drive NPD ↗ — Netguru · Stage-gate (Cooper) (search excerpt, page not opened).

    Stages of work followed by gates where go, kill, hold or send back decisions are made (Robert Cooper's model). Secondary guide. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  10. Market practice

    The 7 principles, practices and processes of PRINCE2 ↗ — PRINCE2 (PeopleCert) USA · PRINCE2 version 7: managing by stages, continued business justification, business case reviewed at stage boundaries. PMI: the PMBOK Guide is built on principles and performance domains; counts differ between editions, so none are given. (search excerpt, page not opened).

    PRINCE2 stages and business case. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  11. Market practice

    PMBOK Guide ↗ — Project Management Institute · PRINCE2 version 7: managing by stages, continued business justification, business case reviewed at stage boundaries. PMI: the PMBOK Guide is built on principles and performance domains; counts differ between editions, so none are given. (search excerpt, page not opened).

    PMBOK Guide built on principles and performance domains; approach-neutral. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  12. Market practice

    Introducing Lead & Lag in Task Dependencies ↗ — Microsoft Tech Community · Vendor blog on lead and lag; community answers on manual dates and unlinked tasks. (search excerpt, page not opened)

    Vendor blog: lead and lag in task links. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  13. Market practice

    Critical Path Not Reflecting in Gantt Chart ↗ — Microsoft Q&A · Vendor blog on lead and lag; community answers on manual dates and unlinked tasks. (search excerpt, page not opened)

    Community answers: manual dates and unlinked tasks break the critical path. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  14. Market practice

    Project Status Report Template ↗ — ProjectManagement.com · Practitioner templates and threads; RAG meanings differ by team. (search excerpt, page not opened)

    Practitioner template: overall status, milestones, risks, next steps. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  15. Market practice

    What content do you put in a status report? ↗ — ProjectManagement.com · Practitioner templates and threads; RAG meanings differ by team. (search excerpt, page not opened)

    Practitioner forum thread on status report contents and RAG meanings. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  16. Market practice

    Business Case Vs Project Charter ↗ — PM Study Circle · Search excerpts only: business case justifies, charter authorises; vision and scope overlaps both and its name is used loosely.

    Exam-prep article: the business case justifies the project, the charter authorises it. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  17. Market practice

    Differences between Vision and Scope and a Project Charter ↗ — ProjectManagement.com (forum) · Search excerpts only: business case justifies, charter authorises; vision and scope overlaps both and its name is used loosely.

    Forum thread: vision and scope, business case and charter overlap and names vary. · Checked 2026-10-19

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  18. Market practice

    GAO Cost Estimating and Assessment Guide — GAO-20-195G (March2020) ↗ — U.S. Government Accountability Office · GAO-20-195G (March 2020), Chapter19, Table23 pp256–257: EV,PV,AC; SV=EV−PV,CV=EV−AC,SPI=EV/PV,CPI=EV/AC. EAC methods require stated assumptions; Daily List points are synthetic budget units.

    Chapter19/Table23 pp256–257 establishes earned-value variances and indices; forecast methods depend on assumptions. Actual primary text read. Does not certify invented Daily List numbers or business-benefit outcomes. · Checked 2026-11-06

Deepest material on this page: L4 — Standards & sources. Where a topic stops short of implementation depth, that is a deliberate coverage decision, not an oversight — see coverage.