Project life cycles and PM artefacts for BAs: charter, schedule, milestones, earned value
Read the project charter, the schedule with its milestones and an earned value report, so you can tell whether the work still matches the need. Written for analysts, not managers.
L1–L4 are part of the Pro pass
L0 Explain simply
Analogy: A holiday plan. Before a trip, a group writes one page. It says where you are going, why, how much you will spend and who decides. Next comes a calendar with checkpoints, such as "at the station by noon". Halfway through, someone asks two questions: how much of the trip is done, and how much money is gone?
A project works the same way. Nina, the for Daily List, wants a calendar connection, so that people see due dates in their own calendar. A runs the project. Sam, the business analyst, makes sure the work still fits what users need.
Three ideas carry this lesson. A is the short note, signed by the sponsor, that says the project may start. The sponsor is the person who backs the project and pays for it. A is the series of stages a project passes through, from first idea to hand-over. Earned value counts the budgeted value of work actually finished; it is not cash received or business benefit. So you can compare it with the plan and with the money spent.
A does not run these papers. Sam reads them, checks them against the real need, and speaks up when they drift.
The limit of the picture: a holiday plan is small and one person decides. A project has a sponsor, a manager and many people, and their wishes can clash.
PLAIN WORDS · 1 in this section
- checkpoints
- points along the way where a payment is checked
PICTURE IT
The picture is the one the lesson above opens with. The table below shows how each part of it matches the work.
THE REAL JOB The picture helps a newcomer see that a project has a signed start note, a calendar with checkpoints, and a regular check of work done against money spent.
- Sign the goal page
- Choose the stops
- Mark the checkpoints
- Count what is done
- Compare with money spent
HOW THE PICTURE MAPS
| In the picture | In the work |
|---|---|
| The one-page goal for the trip | The project charter |
| The stops on the way, from first to last | The stages of the project life cycle |
| Be at the station by noon | A milestone in the schedule |
| How far along the trip you really are | Earned value |
| The money gone so far | Actual cost |
WHERE THIS PICTURE STOPS
- A holiday plan is small, while a project has a sponsor, a manager and many people.
- On a trip you can see how far you have come, but finished work in a project has to be agreed.
- A holiday ends on the day, while a project may change its goal on the way.
- Earned value is budgeted work progress, not business benefit. SV is in budget units, SPI is not calendar speed, and EAC depends on a stated future-efficiency assumption.
HOOK
Goal page, stops, checkpoints, then done against spent.
REMEMBER IT THIS WAY
A sequence: the real steps, in order.
Earned comes first: take away planned for the schedule gap, then take away actual cost for the cost gap.
| In the trick | What it stands for |
|---|---|
| Earned first | earned value |
| Take away planned | schedule variance |
| Take away actual cost | cost variance |
The pattern does not tell you whether the pieces counted as earned really meet the rule for done.
TELL A FRIEND
The charter starts the project, the life cycle is its shape, and compares finished work with the plan and with the money spent.
OFTEN MIXED UP WITH Working with project managers. That topic is about how an analyst and a share the work. This one is about the papers the project manager keeps and what the analyst reads in them.
PRACTISE AND KEEP
Sources for this topic — 18 sources
- Market practice
The charter: selling your project (Project Management Institute library article) ↗ — Project Management Institute · The charter: selling your project (Project Management Institute library article): the charter is a document from the sponsor or initiator that formally approves the project and gives the project manager authority; the sponsor approves it and the project manager often drafts it (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Earned value management tutorial (National Aeronautics and Space Administration, Office of the Chief Financial Officer) ↗ — National Aeronautics and Space Administration (NASA) · Earned value management tutorial (NASA Office of the Chief Financial Officer): schedule variance is earned value minus planned value and cost variance is earned value minus actual cost, with a worked example (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Partnering: project manager and business analyst collaboration (Project Management Institute library paper) ↗ — Project Management Institute · Partnering: project manager and business analyst collaboration (Project Management Institute library paper): the business analyst and project manager share work on the business case, charter, scope and requirements; analyst on product scope, manager on project scope (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Inside the Project Management Body of Knowledge guide, seventh edition: Development Approach and Life Cycle performance domain (Project Management Compass) ↗ — Project Management Compass · Inside PMBOK 7: Development Approach and Life Cycle performance domain (Project Management Compass): a project life cycle is phases from start to end; approaches range from predictive to adaptive, with hybrid between; secondary summary (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
PRINCE2 Agile 2016: tailoring guidance for the PRINCE2 processes (AXELOS publications) ↗ — AXELOS · PRINCE2 Agile 2016: tailoring guidance for the PRINCE2 processes (AXELOS publications): the method is tailored to the project and the processes scale to all project types; justification stays tied to the business case (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Milestones (Celoxis knowledge base) ↗ — Celoxis · Milestones (Celoxis knowledge base): a milestone is a point in time with no duration, drawn as a diamond; vendor help page (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Burndowns considered harmful? (Soliant Consulting blog) ↗ — Soliant Consulting · Burndowns considered harmful? (Soliant Consulting blog): earned value needs a stable baseline, which agile work lacks; practitioner opinion (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Simplified educational illustration
Payments Signal editorial teaching models — Payments Signal
What this simplifies: Daily List, Sam, Nina and the project manager are invented. The actual GAO cost guide supports the earned-value calculations and their limits. Teaching points represent budgeted work, not realised business benefit or days of delay. Real reports, schedules and charters require more context; the full licensed standards were not read.
Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.
- Market practice
Stage-gate process: how gates and stages drive NPD ↗ — Netguru · Stage-gate (Cooper) (search excerpt, page not opened).
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
The 7 principles, practices and processes of PRINCE2 ↗ — PRINCE2 (PeopleCert) USA · PRINCE2 version 7: managing by stages, continued business justification, business case reviewed at stage boundaries. PMI: the PMBOK Guide is built on principles and performance domains; counts differ between editions, so none are given. (search excerpt, page not opened).
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
PMBOK Guide ↗ — Project Management Institute · PRINCE2 version 7: managing by stages, continued business justification, business case reviewed at stage boundaries. PMI: the PMBOK Guide is built on principles and performance domains; counts differ between editions, so none are given. (search excerpt, page not opened).
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Introducing Lead & Lag in Task Dependencies ↗ — Microsoft Tech Community · Vendor blog on lead and lag; community answers on manual dates and unlinked tasks. (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Critical Path Not Reflecting in Gantt Chart ↗ — Microsoft Q&A · Vendor blog on lead and lag; community answers on manual dates and unlinked tasks. (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Project Status Report Template ↗ — ProjectManagement.com · Practitioner templates and threads; RAG meanings differ by team. (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
What content do you put in a status report? ↗ — ProjectManagement.com · Practitioner templates and threads; RAG meanings differ by team. (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Business Case Vs Project Charter ↗ — PM Study Circle · Search excerpts only: business case justifies, charter authorises; vision and scope overlaps both and its name is used loosely.
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
Differences between Vision and Scope and a Project Charter ↗ — ProjectManagement.com (forum) · Search excerpts only: business case justifies, charter authorises; vision and scope overlaps both and its name is used loosely.
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
GAO Cost Estimating and Assessment Guide — GAO-20-195G (March2020) ↗ — U.S. Government Accountability Office · GAO-20-195G (March 2020), Chapter19, Table23 pp256–257: EV,PV,AC; SV=EV−PV,CV=EV−AC,SPI=EV/PV,CPI=EV/AC. EAC methods require stated assumptions; Daily List points are synthetic budget units.
Deepest material on this page: L4 — Standards & sources. Where a topic stops short of implementation depth, that is a deliberate coverage decision, not an oversight — see coverage.