TOPIC 10/4515 MINNOT STARTED

Critical path and work breakdown for BAs

Split a job into pieces with a work breakdown tree, add up the days along each chain of tasks, and find the critical path and the float. A simple schedule skill for analysts.

L1–L4 are part of the Pro pass

L0 Explain simply

Analogy: Cooking a roast dinner. The roast takes three hours in the oven. The vegetables take one. The sauce takes twenty minutes. If you want everything hot at seven, the roast decides when you must start. The vegetables can wait.

A project has the same shape. A (WBS) is a tree that breaks the project scope into deliverables and smaller work packages. Activities to produce them are then scheduled. The is the longest chain of linked tasks, which sets the earliest finish date. Float is the time a task can slip without delaying the finish date.

Sam is the for Daily List. The paid plan must launch on a set date. The asks him to help break the work into tasks and find which ones cannot slip. Even without the manager title, an analyst can read and build a simple schedule.

The picture has a limit. Several dishes can cook at once, but the cook and oven still have limits. A team has a limited number of people, so tasks may have to wait for a free person.

PLAIN WORDS · 1 in this section
deliverables
things that must be handed over

PICTURE IT

The picture is the one the lesson above opens with. The table below shows how each part of it matches the work.

THE REAL JOB The picture helps a newcomer remember that the slowest chain of tasks decides the finish, and that other tasks have spare time.

  1. Split the job into a tree
  2. Add the links and days
  3. Add up each chain
  4. Pick the longest chain
  5. Find the float on the rest
Finding the critical path

HOW THE PICTURE MAPS

How each part of the picture matches the work
In the pictureIn the work
The whole dinner on the tableThe whole job at the top of the tree
The roast, the vegetables and the sauceThe main parts of the work
The roast that takes longestThe critical path
Vegetables that can wait a littleTasks with float
Serving at sevenThe finish date

WHERE THIS PICTURE STOPS

  • One cook can do many things at once, but a team has a limited number of people.
  • A recipe gives sure times, but task lengths are estimates.
  • Dinner is cooked once, but a schedule changes as work goes on.
  • A WBS describes deliverables/work packages; the schedule sequences activities. Total float is shared along a path: C and D cannot each spend the same one-day allowance independently.

HOOK

Split the job, add up the chains, protect the longest.

REMEMBER IT THIS WAY

A rule of thumb: if you see this, think that.

Usually the longest chain of linked tasks sets the finish date, so add up the days along each chain and guard the longest first. Tasks on shorter chains have float.

What each part of the trick stands for
In the trickWhat it stands for
longest chainthe critical path
shorter chainstasks that can slip with float

If the team is short of people, tasks on shorter chains can compete for the same person and delay the finish.

TELL A FRIEND

Break scope into deliverables, then schedule their activities. The longest dependency path sets the simple model’s finish; C and D share the shorter path’s one day of total float.

OFTEN MIXED UP WITH The RAID log and item tracking. That topic tracks risks and open items. This one shows which tasks put the finish date at risk.

Sources & standards — 1 source
  1. Market practice

    GAO Schedule Assessment Guide — GAO-16-89G (December2015) ↗ — U.S. Government Accountability Office · GAO-16-89G (December 2015), WBS discussion p21, Best Practices 6–7 pp75–77 and92–93: dependency-derived critical/near-critical paths, shared total float and free float. Daily List durations are synthetic.

    WBS deliverables versus schedule activities; valid critical and near-critical paths; shared total/free/negative float. Actual primary pp21,75–77,92–93 read. Source Figure35 inspected separately; no artwork copied in this content change. · Checked 2026-11-06

PRACTISE AND KEEP

Sources for this topic — 6 sources
  1. Market practice

    What is a work breakdown structure (University of Maryland enterprise project management) ↗ — University of Maryland · What is a work breakdown structure (University of Maryland enterprise project management): the breakdown must include all of the work in the scope and nothing outside it (search excerpt, page not opened)

    University page. States the rule that the breakdown must hold all of the work and nothing outside it. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  2. Market practice

    Float and slack: total float versus free float explained (Rework) ↗ — Rework · Float and slack: total float versus free float explained (Rework): float is the delay a task can absorb, and the critical path is the chain with no float (search excerpt, page not opened)

    Vendor guide. Defines float as the delay a task can absorb and the critical path as the chain with no float. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  3. Market practice

    Critical path method (concept note) ↗ — dsebastien.net · Critical path method (concept note): the critical path is the longest chain of dependent tasks (search excerpt, page not opened)

    Concept note. Describes the critical path as the longest chain of dependent tasks. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  4. Market practice

    Work breakdown structure: definition, levels and examples (Instagantt) ↗ — Instagantt · Work breakdown structure: definition, levels and examples (Instagantt): split the work first and schedule it second, and keep sibling pieces from overlapping (search excerpt, page not opened)

    Vendor guide. Says to split first and schedule second, and that pieces must not overlap. Search excerpt only. · Checked 2026-10-18

    Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.

  5. Simplified educational illustration

    Payments Signal editorial teaching models — Payments Signal

    This site's own simplified teaching models. · Checked 2026-07-12

    What this simplifies: Daily List, Sam and the tasks are invented, and the days are teaching numbers. GAO-16-89G was read for WBS, dependencies, critical paths and shared/free float. The six-task Daily List network is independent teaching material, not the GAO construction example. Real schedules also constrain resources and calendars.

    Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.

  6. Market practice

    GAO Schedule Assessment Guide — GAO-16-89G (December2015) ↗ — U.S. Government Accountability Office · GAO-16-89G (December 2015), WBS discussion p21, Best Practices 6–7 pp75–77 and92–93: dependency-derived critical/near-critical paths, shared total float and free float. Daily List durations are synthetic.

    WBS deliverables versus schedule activities; valid critical and near-critical paths; shared total/free/negative float. Actual primary pp21,75–77,92–93 read. Source Figure35 inspected separately; no artwork copied in this content change. · Checked 2026-11-06

Deepest material on this page: L4 — Standards & sources. Where a topic stops short of implementation depth, that is a deliberate coverage decision, not an oversight — see coverage.