Tom counts the days nobody worked on the change
In simple terms / 01
What this means in plain language
Tom maps a small change at Daily List and finds that two and a half of nine days were work. Testing took half a day, and the rest was waiting.
Complete lesson / 02
Understand the full idea, step by step
A coffee takes two minutes to make, yet the queue takes ten. If you want coffee sooner, you do not hurry the barista. You shorten the queue.
This brief follows a tester who draws the journey of one change and finds that most of its days were spent waiting.
What matters is the two kinds of time: days when someone works on the change, and days when it sits.
Evidence & review / 03
Evidence & review
The date on this lesson is when it went up on Payments Signal, not when its material was written — most of these were brought across from an earlier catalogue in a single run, which is why so many of them share a date. What the lesson says about the world is dated by the review above and by the sources below it.
A made-up change in a made-up to-do app, mapped from idea to release, using lean value stream ideas as seen in search excerpts.
What this brief simplifies: Fiction labelled SYNTHETIC / TRAINING ONLY. Real maps show more than time. The ISTQB agile test leadership chapter on value streams was seen only as a chapter theme, and no page was opened.
Sources for this brief — 4 sources
- Market practice
Understanding the fundamentals of value stream mapping (Lean Enterprise Institute) ↗ — Lean Enterprise Institute · Value stream mapping draws the steps and the flow of information that bring a product or service to the customer (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail. Prior reading/history preserved; business-stream scope is additional, not a replacement.
- Market practice
What is lead time in value stream mapping (Miro page) ↗ — Miro · Lead time is the elapsed time from order to delivery, and a value stream map splits it into working time and waiting time (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Market practice
The seven wastes of lean (TeamGuru guide) ↗ — TeamGuru · The seven wastes of lean include waiting and defects; lists differ between sources (search excerpt, page not opened)
Found through a web search; the page was not opened (search excerpt, page not opened). Licence terms were not read, so put it in your own words and do not quote it. Open the page and confirm what it says before relying on any detail.
- Simplified educational illustration
Payments Signal editorial teaching models — Payments Signal
What this simplifies: Daily List, its numbers and the people are invented. A real value stream map shows more than time, such as what each step passes on. This lesson follows time only.
Used wherever diagrams, scenarios, figures, or example values are didactic constructions rather than sourced facts; every such use carries a simplifications disclosure. All people, companies, banks, and list entries in examples are fictional.